The MOD has announced the signature
of the Type 26 Manufacture Phase 1 contract, covering the first 3 of 8 planned
Type 26 frigates. First steel will be cut in the next few weeks, and perhaps we'll hear about names too.
The latest, and presumably final CGIs released show "fat cheeks" on the superstructure that give long passageways around the bridge, good for situational awareness and for the placement of small weapons for anti-swarm, anti-FIAC defence. The mast design has been further refined, and the Sea Ceptor cells arrangement has been finalized, with the launchers being the same "mushrooms" tubes used on the Type 23s refitted with the missile. The number of cells has not changed, while the export design targeted at Canada (and, with further modifications, at Australia) has been shown replacing the CAMM cells with an additional MK41 module (from 24 to 32 cells).
![]() |
| The latest images show what Type 26 will look like |
![]() |
| This model of a Type 26 proposal for Canada shows an extra MK41 module instead of CAMM cells. |
The contract is described as a 3.7 billion pounds deal, but
this figure urgently needs to be clarified. Government seems to be playing
games by using it: on one side, it is giving the impression that it is
committing more money than it actually is; on the other it makes it impossible
to figure out how much each of the three vessels is costing. Unfortunately,
whatever the exact amount, the answer is: a bloody lot.
The confusion is due to the MOD
having already signed contracts worth more than 1.9 billion pounds to get to
this point.
The first big Type 26 contract dates
back to 2010 and was a 127 million, 4-years contract for designing the new
vessel.
In February 2015 this was followed
by an 859 million Demonstration Phase deal, which included selection of suppliers
and long lead items orders, plus the construction of three shore-based test facilities
to de-risk key parts of the vessel. David Brown built a test facility to
demonstrate the new cross-connect gearbox developed for the Type 26; General
Electric Power Conversion built the Electric Power Generation and Propulsion
facility to de-risk the power segment of the ship; and the Combat System Land
Based Integration and Test laboratory demonstrated the entire Combat System.
This investment should pay dividends later on by ensuring that all works as
intended, preventing many of the teething issues associated with new systems in
new ships.
In march 2016, contracts for 472
million in long-lead items including side doors, helicopter handling system,
bow sonar domes and other parts was announced.
In July, 183 million pounds were
added to procure the MK45 gun systems (including automated ammunition handling,
gun fire control system and ammunition) for the first three ships; plus another
system to be installed ashore as integrated training facility.
In December 2016 another large
contract followed, for 380 millions, covering chilled water plants, hangar
cranes, hatches and watertight doors, membrane sewage treatment plants,
steering gear and stabilizers.
![]() |
| The long list of suppliers and systems already under contract and at work due to earlier Demonstration Phase contracts |
Most, but not all, of these almost 2
billion pounds, which have been converted in a long list of parts already on
order / delivered / being delivered for the first three vessels, have
effectively been announced a second time, because they are included in the 3.7
billion deal.
A part of what was already expended
is counted separately: probably the non-recurring cost of setting up the shore
test facilities, the gun training system, and other voices of expenditure.
Whatever the exact division of
costs, the pricetag of the Type 26s remains disconcerting, because most of its
known systems and capabilities are non-developmental, funded by different
budget lines, or straight out recycled.
The ship will have a newly designed
gearbox but will use well known MT30 gas turbines already used all around the
world; and it will have a CODLOG (Combined Diesel or Gas) which is arguably the
simplest configuration involving a gas turbine. A well understood, definitely
non innovative propulsion system and, arguably, in some ways a step back from
the Type 23’s CODLAG (Combined Diesel and Gas) which allows the ship to exploit
all of its installed power for obtaining max speed.
The ship’s main defensive weapon is
the CAMM / Sea Ceptor missile, which is developed and acquired under the
Complex Weapons budget line and which is already being procured for the Type 23
life extension and capability sustainment project, with three vessels already
refitted.
Type 26 will have more Sea Ceptor
cells (48 in two well separated silos, fore and aft, of 24 cells each; versus
32 all on the bow for Type 23), but will essentially inherit most of the
arsenal from the retiring Type 23s.
The ship’s gun is new to the Royal
Navy, but is the latest iteration of a system which is decades old and used in
hundreds and hundreds of exemplars on US Navy and other nations’ vessels all
around the world. The only developmental addition is the automated ammunition
handling system and depot, but similar systems are already operational around
the world and hardly break the bank.
The main radar is planned to be the
Artisan 3D, already operational on Type 23, from which it will migrate to the
new hulls.
The Type 26’s main offensive power
will entirely depend from three 8-cell MK41 vertical missile launchers. Again,
a new system in Royal Navy use, but well over a thousand such VLS modules are
operational in the US Navy and elsewhere. Their cost is far from prohibitive,
and they are non developmental and well understood.
What is not well understood is what,
if anything, the Royal Navy will put into these VLS. It currently has no
weapon, in service or planned, which is ready for MK41. The Tomahawk is an
obvious candidate, but the small Royal Navy stock of the missile is all in the
encapsulated variant for submerged launch from submarine’s torpedo tubes.
Harpoon is going out of service next
year, leaving the Royal Navy bare of any heavy anti-surface missile, and the
Type 26’s offensive power is entirely dependent on “Maritime Future Offensive
Surface Warfare capability”, a programme which is funded under the Complex
Weapons budget (so entirely additional to other Type 26 costs) and which only appeared
in the Equipment Plan in the 2016 edition. We know absolutely nothing of its
exact aims and of the timeframe associated with it.
Light guns for ship’s self defence
will come from retiring Type 23s, as will a good part of the decoy outfit, including
the S2170 anti-torpedo system.
The towed array sonar Type 2087 also
comes straight from the Type 23s. We don’t yet know about the hull-mounted
sonar on the bow. Maybe this, at least, will be new. Or maybe no.
The exact details of how equipment
will migrate between Type 23s and Type 26 is not known. The MOD was asked about
it in a few occasions, but offered very little in terms of answers. It is
obvious that a Type 23 will have to leave service early to be dismantled and
robbed of parts to enable the fitting out of a new Type 26 unless a few new
sets of equipment are purchased.
According to admiral sir PhilipJones, three such “extra” sets have been procured, for the first three vessels,
to ensure that there is no need to shrink the fleet early to fit out the first
new Type 26s. After that, the equipment for the following vessels will come
from the withdrawn 23s.
Admiral Sir Philip Jones: Yes, that is absolutely true. One of the things that we think will de-risk the Type 26’s entry into service is the fact that much of its equipment will have been tested and proved by operating on the Type 23 frigates, in particular the Sea Ceptor missile system, the Artisan Type 997 air surveillance radar and a number of other things.The Type 23 that we bring in to pay off has to be the donor platform to the next Type 26. We’ve bought new equipment for each of the three first Type 26s, to sort of get the class going, if you like; that is part of the long-lead items we have procured. So we will then have, as it were, a residue of decommissioned Type 23s’ equipment, which we can return and recycle, and deliver to the builder to fit into the Type 26. We won’t have to bring one in and stop it operating before we send it north; we’ve deliberately factored that in. I think that means that we will have much more resilience and already-tested equipment in that ship, which will bring it into service much faster than we’ve seen before.
Exactly what these “extra” sets
include is not clear. It seems highly unlikely that there will be extra Type
2087 sonars, for example. Probably we are only looking at the essential pieces.
In theory, the extra sets could afterwards
ease the fitting out of the Type 31e frigate if it will ever actually come
together and if there will ever be more than 5 of them. In theory, purchasing
three extra sets of parts gives the Royal Navy enough kit for 16 frigates
instead of 13. Whether this benefit is ever realized is anyone’s guess.
The Type 26 introduces very little
in the way or truly new systems to the fleet. There is a hope that the Royal
Navy will be able to improve the crucially important self-defence decoy fit by
replacing current fixed-tube launchers with something like the CENTURION
trainable decoy launcher, which can adjust to fire the decoy in the best
possible direction for maximum effect, without the entire ship needing to
change course first. This is extremely important in light of the development
abroad of faster and faster anti-ship missiles which will not wait for the ship
to manoeuvre into a new position. But even this very, very modest development
is currently a mere hope: data about Type 26 so far makes no mention of this
and earlier attempts by the RN to invest in this area were frustrated by lack
of funding.
![]() |
| CENTURION trainable decoy launcher |
It even seems that the Type 26 will not carry ship-launched anti-submarine torpedoes. For years now there has been no mention of migrating the Type 23’s magazine torpedo launchers. In absence of a vertical launch anti-submarine weapon such as the American ASROC, the Type 26 will be entirely dependent on the embarked helicopter for prosecuting the submarines it picks up on the sonar.
While the limitations of the
ship-launched light torpedo are well understood (being close enough to a
submarine to employ it probably means the submarine has already fired its own
much larger torpedoes), it seems rather disconcerting to do away with them
entirely. And if they aren't fitted, this is another capability the Type 26’s budget is not funding.
How the ship can be quite so
expensive despite all of the above is mysterious. We are light years away from
the affordable pricetag that had been the target of the programme, yet many of the big-ticket items are not even contributing to the cost.
We are left to wonder whether spreading
the build on two shipyards (Scotstoun and Govan) is at least partially
responsible. Earlier plans included spending serious money on finally building
a single, capable “frigate factory” plant, but this would have meant closing
one of the current two yards, and this was unpalatable. One look at the
two-site Type 26 construction strategy, however, is enough to see how much more
complication, risk and waste of time (and, inexorably, cost) it adds.
Above, the single-site shipyard proposal.
BAE Systems two-shipyards Type 26 assembly strategy.
The Type 26 is also now described as a 157 men ship. Earlier, the “Core Crew” had been given as 118. To be fair, however, 118 probably excluded elements such as the embarked helicopter flight, which are very much an integral part of what makes a warship work. Probably, 157 is not sign of a step away from automation, but merely a more complete and realistic indication of what it takes to make the warship operate. In 2012, the Royal Navy described the 118 core crew as needed for mere “Float, Move and Self Protect” activities, with ASW specialist “packets” coming separately, along with all other teams needed for the mission. There is space for a further 51 souls (208 bunks in total) to be embarked to operate systems carried in the Mission Bay or as reinforced boarding teams or for other necessities.
The Type 26 is also now described as a 157 men ship. Earlier, the “Core Crew” had been given as 118. To be fair, however, 118 probably excluded elements such as the embarked helicopter flight, which are very much an integral part of what makes a warship work. Probably, 157 is not sign of a step away from automation, but merely a more complete and realistic indication of what it takes to make the warship operate. In 2012, the Royal Navy described the 118 core crew as needed for mere “Float, Move and Self Protect” activities, with ASW specialist “packets” coming separately, along with all other teams needed for the mission. There is space for a further 51 souls (208 bunks in total) to be embarked to operate systems carried in the Mission Bay or as reinforced boarding teams or for other necessities.
The MOD is being very vague about
timeframes for entry in service. What once was 2021 had already become 2023 and
might now be closer to 2025, with the MOD talking of “around the middle 2020s”.
It won’t be earlier than 2023, might be 2025. This is bad news as it means
shrinking the fleet or delaying further the exit from service of the aging Type
23s. HMS Argyll was meant to bow out in 2023, followed by the others roughly
with a yearly drumbeat. This will have to change unless the fleet is to dramatically
shrink.
While we wait for the Shipbuilding
Strategy and for a plan for the Type 31e frigate that is supposed to complement
Type 26, it is hard to rejoice for Sunday’s announcement. It was a key, much
delayed and long expected development, definitely overdue, but it brings forth
unpleasant questions. How can this ship cost so much? How can british
shipbuilding go on if this is the best price it can offer?








