Army plans
In April 2014, the MOD decided to
split the massive “Mounted Close Combat Capability Change” programme into four:
-
Armoured
Cavalry 2025
-
Armoured
Infantry 2026
-
Armour;
Main Battle Tank 2025
-
Mechanized
Infantry 2029
The date at the end indicates the
desired completion time. The budget for the Mounted Close Combat
super-programme was 17.251,83 million pounds.
Data released this year, and current
to September 2015, reveals that the Armoured Cavalry programme has a budget of
6831,55 million, for procuring, putting in service and supporting for the first
few years the Ajax fleet.
The Armoured Infantry programme is
chiefly composed by Warrior CSP, but the army also “aspires” to finally
launching the Armoured Battlegroup Support Vehicle programme. The budget is
currently given as 2176,45 million, but since ABSV is yet to come and the
Warrior CSP procurement hasn’t yet been contracted, the sum is destined to
grow.
No additional update is given on the
status of MBT 2025 and MI 2029. Assuming the overall budget is still 17
billion, there are 8243,85 million to commit to the missing pieces, the biggest
of which is clearly going to be the Mechanized Infantry Vehicle 8x8.
The Challenger 2 Life Extension
Programme, another initiative that is navigating a tormented and endless path
to a Main Gate point that never seems to arrive, was described as having a
budget going from 1.2 billion to 700 million. The latest figure I’ve come
across is 920 million.
Even 700 million pounds are quite a
lot of money for a Life Extension Programme which is not expected to touch the
gun and that will not replace the powerpack. It is hard to say why changing
sights and communications should cost so much on Challenger 2 when a similar
programme in France is going on for some 300 million euro.
Is it an implicit admission that
Challenger 2 obsolescence is truly that desperate…?
We know very little about the MIV
programme, too. The latest words of general Nick Carter suggest a requirement
for 4 battalion sets (two battalions for each “Strike” brigade), which is one
more than was planned under Army 2020 (one mechanized battalion in each of the three Reaction Force brigades). There are clear requirements for a
multitude of variants, including mortar carrier, ATGW and ambulance, but there
is no certainty that money will be there to actually do something about it.
Meanwhile, there have been reports
about the British Army being very interested in purchasing American
Joint Light Tactical Vehicles as solution for the Multi Role Vehicle Protected requirement. Due for
production in the tens of thousands, the JLTV might be the only product with a
realistic chance to achieve a pricetag close to the MOD objective of 250.000
pounds per vehicle.
The MRV-P programme remains, in my
opinion, somewhat confused. Its relationship with existing vehicles such as
Foxhound, Husky and Panther is unclear, and the numbers indicated for the first
purchase are too low: if there is no money for greater numbers and if there
isn’t actual clarity about what to do with it, the British Army should not add
yet another vehicle to its already vast collection.
Clarity is needed, first of all. The
British Army should also determine the future of Light Protected Mobility
Battalions, and act consequently: if they are to be serious warfighting tools,
they should not depend on old Land Rover WMIKs to provide firepower support to
the Foxhounds. Mobility, but moreover protection, are unequal, with the Land
Rover at serious disadvantage. Purchasing more Foxhounds, in WMIK and in
Logistic configurations, would give these units a whole different level of
effectiveness.
It is also necessary to think about
how to distribute Husky and MRV-P, and how to move from the first to the second
over time.
General Carter also candidly
confirmed to the Defence Committee that the “defence engagement battalions”
will be small (just 300 men) in no small part due to the need to recoup
manpower to direct towards the Strike Brigades and the other units needed to
make it feasible to deploy at Division scale, as mandated by the SDSR. Two to
five infantry battalions will be downsized and re-orbated, meaning that the
manpower margin recouped varies from 500 to 1300 men.
Beyond the obvious (freeing up
manpower without being allowed to disband battalions and face capbadge
bunfights), the Defence Engagement battalions are supposed to become the go-to
units when it comes to training, mentoring and helping friendly forces abroad.
Supposedly, these battalions will be elite units, containing a greater number
of officers, SNCOs and specialists, but there is every reason to be doubtful in
front of the claim: where are those specialists going to come from, considering
that the manpower is already an issue now?
Apache
There are now an official
announcement and a deal signed for the procurement of 50 Apache at the Block
III standard, and this is good news, because it hopefully dispels the risk of
seeing the number dropping even further.
The confusion around the Apache situation
endures, however, since the MOD, Boeing and everyone else appear unable to
provide details and a definitive answer to the question: is it a
remanufacturing project, or a new build programme?
The answer seem to be: it is a
remanufacturing project, but so much of the helicopter will be newly built that
confusion is legitimate. Existing Apache AH1 will be dismantled and the valid
systems and components will move across to the new machines, receiving the
upgrades and changes needed.
The Apache remanufacturing involves
a new rotor, new and more powerful engines, updated sights and targeting
system, updated radar, newly built airframe, data link 16, manned-unmanned
teaming and other upgrades. The US Army is rebuilding all of its own Apaches,
uplifting them to AH-64E, and will also procure around 60 wholly new as
replacements for losses and attrition.
The first british AH-64E is expected
to come out of factory during 2020, and the In Service Date is given as 2022. The
new airframe, made of composites and slightly modified to better accommodate
the Block III systems, comes with a life of 10.000 hours. It should be less
prone to corrosion issues, despite the lack of proper navalization: the US Army
has been bringing the Apache out on ships more and more frequently in the
Pacific theatre, so the British Army should not have any grave issue. Manually
folding rotor should come as standard.
The AH-64E won’t be a naval
helicopter, but the Apache AH1 never was, either. The addition of some features
(including emergency floatation gear) over time remains desirable to make
shipboard operations simpler and safer.
Boeing and MBDA have just completed
a series of MOD-funded Brimstone launches from an AH-64E, and the results have
been good. The MOD hopes to replace Hellfire in 2021, and Brimstone, offered by
MBDA as the Future Attack Helicopter Weapon, is the obvious choice. An
integration contract should materialize sometime in the near future, so that
the AH-64E can enter service with it as its main weapon.
The MBDA video about FAHW is very interesting, and it shows two important features: airburst detonation mode and anti-air employment of Brimstone. The US Army has experimented ground-launched Hellfire missiles as anti-UAS weapons, and a similar capability for Brimstone, extending also to larger and more challenging targets (such as the KA-52 in the video) would be particularly helpful for British Apaches which have never been equiped with Stinger missiles nor with Starstreak, despite a demonstration campaign carried out years ago.
P-8 Poseidon and Sentinel R1: the future of ISTAR
The regeneration of MPA capability
is finally confirmed and on the move, and we also have a delivery schedule:
2 aircraft will be ordered in 2017
for delivery in April and December 2019 (Production Lot 8)
3 aircraft will be ordered in 2018
for delivery during 2020 (Production Lot 9)
4 aircraft will be ordered in 2019
for delivery in 2021 (Production Lot 10)
Unless there are delays on the US side, these dates imply that the UK Poseidons will come with Increment 3 standard. It should also come with 6 rather than 5 workstations, following the US and Australian decision to fit the additional console to better exploit the growing capabilities of the type.
What we do not know yet is how (or
even if) these airplanes will be armed. The UK has elected to follow a pure Off
The Shelf approach for the purchase, so that no british weaponry will be
integrated, at least for now. The question thus becomes whether or not the UK
will order a stock of US torpedoes (and wing-kits for their deployment from
altitude) and whether anything will be done on the anti-ship missile front.
With the loss of the Nimrod, the RAF also lost its last anti-ship platform,
after all, and it is not clear if the old stock of air launched Harpoon is still in storage and if it could still be used.
The current thinking in the MOD is
that the P-8 Poseidon will also replace Sentinel R1 in the 2020s, but how this
will be done is not, at this stage, clear. An obvious solution is trying to
obtain from the US the export of their AN/APQ-154 Advanced Airborne Sensor radar pod,
which is in development specifically for the P-8 and is also serving as base
for the radar proposed by Raytheon for the USAF’s JSTARS replacement programme.
Fitting a different radar sensor is
also an option: the P-8 can take it, and can carry out long range overland
radar surveillance, despite flying tipically a bit lower than Sentinel.
One issue, already underlined by RAF
officers, is that 9 aircraft are too few to properly cover both sea and land
requirements. An additional batch of 3 aircraft would help, and the number 12
has circulated at times in the period leading up to the SDSR: if Sentinel will leave
service in the early 2020s, increasing the number of P-8s and adding a
land-surveillance radar will be very important.
As part of stealth cuts meant to
free up money and manpower to make the investments of the SDSR 2015 possible,
the RAF is due to cut the Sentinel R1 fleet from 5 to 4 aircraft and from 10 to
5 crews, while also reducing the extent of upgrades initially proposed for the
platform. Air Commodore Dean Andrew, commander
of the RAF ISTAR Force, however,
has made it abundantly clear that he
opposes this approach and will try to have the idea shredded.
Unfortunately, time is not on his side, considering that the cut is scheduled
for September.
The situation is complicated by the
ever present problem of manpower: the RAF was granted a small uplift in
personnel number in the SDSR, but at the same time it was loaded with a great
number of requests which all require manpower. Supposedly, the Sentinel’s
companion, the Shadow R1, should see the fleet expanded from 5 (+1 currently
without mission kit, only good for training) to 8. There is a proposal to
uplift the number of combat-ready Sentry crews from 5 to 12 by 2021. There will
be Poseidon to man. There will be 20 Protector, which much greater endurance,
in place of 10 Reaper, and these might have no pilot on board but require a
great number of people back in the base. 14 C-130Js are now expected to remain,
and the number of combat jet squadrons will now (thankfully) stay around 9,
rather than drop to 6.
It is very clear that manpower is a
problem. Poseidon alone is likely to require as many men as the SDSR gave, and
maybe more, so the RAF needs to shift manpower around from within the current
totals. If someone gains, someone else is bound to lose.
And, obviously, it also takes time
to shift people around, re-train personnel and/or recruit and train new people.
There is an expectation that the
CBRN mission will transfer to the Army, so the RAF Regiment is probably due to
shrink by a sizeable number in the coming years, but the manpower margin is not
immediately transferable and will not, in itself, solve the problems.
I do not think I’d feel surprised at
all if the extra AWACS crews and additional Shadow R1 ended up never
materializing. They seem to me to be commitments from which it will be easy to
retreat in silence and darkness.
A number of upgrades for Sentinel
have been funded and will proceed. These include a maritime radar mode for the
radar, to appear sometime in 2018; increased SAR resolution and improved SatCom
are also on the list, all to be delivered during 2017 and 2018.
A number of other upgrades remain,
presently, not funded: these include adding ELINT capability, upgrading the
cockpit and mission consoles and adding a Long Range Optical Sensor (the DB-110
used in the RAPTOR pod was mentioned in the past few months) to complement the
radar.
Sentinel is a precious ISTAR asset
and delivers extremely valuable battlefield surveillance that should not be
lost, so its future (and eventually its replacement) remain a topic to follow
with attention.
Meanwhile, the MOD has signed a deal
to procure Protector itself through a hybrid Foreign Military Sale process,
which will enable the RAF to work together with GA-ASI
to modify their “Certifiable Predator B” to turn it into Protector.
The Certifiable Predator B is an
internal effort started by GA-ASI to build a more capable Reaper complete of
Due Regard sensor capability for flight in non-segregated airspace. It also
comes with a new and longer wing carrying more fuel, giving an endurance in the
40 hours region.
The wings also should offer greater
payload margins: an image released by GA-ASI shows 4 triple Brimstone racks and
2 Paveway bombs installed on a Protector. This would not be possible on Reaper,
as the third station on its wing (never really employed) can only carry some 70
kg.
Certifiable Predator B with Brimstone racks. |
The Protector should massively expand the capabilities of the RAF, but it will be interesting to see if some efforts will be made to make it more survivable in presence of some enemy air defence. The Reaper is pretty much defenceless, but as Protector becomes more capable and more expensive, it would make sense to try and make it less vulnerable.
It could be worth a try to adapt the
self-defence pods currently employed by Tornado GR4, since they have been
upgraded and improved in recent times (first the BOZ dispenser of Flares, and
lastly the Cerberus EW pods, which have been upgraded to “Common Jamming Pod,
with electronics equal to those of the Typhoon’s DASS and with the same towed
radar decoy added in as well) and could still be useful for years after the
Tornado will be gone.
Weapon and sensor choices will also
be important. Integrating Brimstone and Paveway IV seems the right thing to do,
unless the special (and rather advantageous) current agreement with the USAF
for access to their stocks of Hellfire and GBU-12 is to continue.
The RAF also spoke, back when the
programme was known as SCAVENGER, of common pods to be developed and certified,
with the ability to rapidly switch the payload within them to enable rapid
evolution of the drone’s capability. This is a smart approach, and hopefully
will still feature in Protector.
The UK is also looking at setting up a UAS School in the UK, since the USAF is already hard pressed to train its own UAS crews, and will struggle to take care of foreign needs. Simulation should enable aircraft-free training, but the actual solution has yet to be chosen.
The UK is also looking at setting up a UAS School in the UK, since the USAF is already hard pressed to train its own UAS crews, and will struggle to take care of foreign needs. Simulation should enable aircraft-free training, but the actual solution has yet to be chosen.
A long sundown for the Hawk T1
With 208(R) Sqn now disbanded, the
Hawk T1 is no longer used in training of fast jet crews, but it remains
employed for air support to operational training, playing Aggressor in air to
air battles; helping to qualify JTACs and assaulting Royal Navy ships to let
them hone their air defence skills. The Hawk T1 also is the Red Arrows’ mount.
It will be around for many years
still, yet its sundown is due to begin relatively soon. The MOD has decided
that 736 NAS will lose its Hawk T1s in 2020; followed by 100 Sqn around 2027
and finally by the Red Arrows in 2030 (or by 2035).
The Royal Navy is the first to have
to grapple with the problem, which is also connected to the current arrangement
for EW and threat simulation coming to an end in the same timeframe. Currently,
a fleet of Falcon DA20 provided and crewed by Cobham provide 6500 hours a year
of service in support of training exercises, jamming radars and electronically
simulating aircraft and weapons. The Royal Navy is the main customer of the service,
with 3500 hours, followed by 2500 for the RAF and 500 for contingencies.
The MOD has launched a new project
for procuring a new solution to these requirements, under the name ASDOT, Air
Support to Defence Operational Training. Interestingly, Qinetiq and Thales have
agreed
on jointly offering the Textron Scorpion aircraft as platform for the new
service.
The pick is somewhat puzzling,
because the Scorpion does not appear to be particularly suited to be an
Aggressor, lacking in speed and agility. Even as replacement EW platform it
seems not entirely suited, due to having only 2 crew on board, against a
typical minimum of 3 for the Falcon 20.
The Scorpion will have no trouble
carrying the panoply of pods employed by the Falcon (radar simulator pod, jammer
pods, RAIDS pod) and it also has a weapons bay that could be used for
additional payloads, but it might take some work to turn it into a proper
replacement for Falcon.
It should excel at supporting JTAC
and Fire Support Teams training, though.
ASDOT will be an interesting
programme, judging by this beginning. We’ll see if and how 736 NAS will survive
the award of the ASDOT contract: will the service provider be tasked with all
the flying too, or will the current Hawk T1 part of the job still be carried
out by navy pilots? It is not clear at this stage.
For RAF Red Air purposes, there have
been suggestions which have included using some of the Typhoon Tranche 1, in
order to have an enemy with the necessary speed and agility and sensors.
Fixed and Rotary Wing crew training
With the award of the contract for the renewal of the rotary wing training fleet, the Military Flying Training System has made a decisive step forwards. However, concerns remain: the SDSR 2015 has brought a sizeable uplift in the number of crews to be trained, and while the number of instructors planned has been adjusted, the number of training aircraft has not been.
The SDSR 2015, thanks first of all to the purchase of the P-8 Poseidon, has also re-introduced a sizeable training requirement for mission crew. The plan for training "back-seaters" has not been detailed yet, but is something that requires some thought.
In the Rotary Wing arena, we will have to see if Joint Helicopter Command will be able to pursue a further element later, that of "surrogate" helicopters for training. The idea emerged a while ago, of procuring cheap helicopters to equip as "flying simulators" to employ in some Wildcat and Apache training phases to save money.
It is to be seen what will happen to the Army's advanced helicopter crew course in Middle Wallop, as well.
An element of advanced training has been designed thanks to the formation back in April of 202(R) Sqn in RAF Valley. This "new" unit is actually the re-named and re-purposed SARTU (SAR Training Unit) which was no longer required in its original role of preparing SAR crews since that incumbence has now been moved under the Department for Transports.
202 Sqn will now provide overland and overwater winch training along with day/night mountain flying techniques and NVD operations for all RN/ RAF abinitio pilots and crewman who are destined for Support Helicopter (SH) roles. In addition, a new course is being developed to offer bespoke training to current experienced SH operators in order to enhance their skill sets.
Air Weapons
Brimstone 2 has been finally put into service, after several months of delays due to difficulties emerged during development. The weapon is now operational on Tornado GR4 and is being integrated on Typhoon.
Typhoon weapons integration is finally getting serious, with Meteor, Storm Shadow and Brimstone to enter service over the next two years.
The AESA radar has finally been flown for the first time (several months later than was hoped last year) and hopefully its integration will be part of the Phase 4 Enhancements, post 2018.
Work is also ongoing on the new bunker-buster warhad for Paveway IV, which has begun validation trials. Discussions have also already begun on ensuring that the Block IV software for the F-35 will include functional integration of the bunker-buster warhead variant.
SPEAR 3 has been dropped for the first time, from a Typhoon. The weapon is planned for integration on the F-35 sometime in the first half of the 2020s, as part of the Block IV programme, which is expected to also include Meteor.
Royal Navy UAS plans: ambitions, but no money
Brimstone 2 has been finally put into service, after several months of delays due to difficulties emerged during development. The weapon is now operational on Tornado GR4 and is being integrated on Typhoon.
Typhoon weapons integration is finally getting serious, with Meteor, Storm Shadow and Brimstone to enter service over the next two years.
The AESA radar has finally been flown for the first time (several months later than was hoped last year) and hopefully its integration will be part of the Phase 4 Enhancements, post 2018.
Work is also ongoing on the new bunker-buster warhad for Paveway IV, which has begun validation trials. Discussions have also already begun on ensuring that the Block IV software for the F-35 will include functional integration of the bunker-buster warhead variant.
SPEAR 3 has been dropped for the first time, from a Typhoon. The weapon is planned for integration on the F-35 sometime in the first half of the 2020s, as part of the Block IV programme, which is expected to also include Meteor.
Royal Navy UAS plans: ambitions, but no money
The Royal Navy has tried to launch a
couple of UAS programmes in the 2016 Budget Cycle, but at least one of the two
did not receive funding, Jane’s reports.
The Navy had hoped to launch the
Flexible Deployable UAS programme in order to procure a replacement for the
current flights of contractor-owned, contractor-operated Scan Eagle UAS. The idea for FDUAS was not
particularly detailed in public, but the Navy was looking for a “Scan Eagle
plus” system offering greater “Find” capability. Purchasing a number of RQ-21
Integrator, the larger brother to Scan Eagle, already selected for USMC and US
Navy use, could have possibly been a solution on the table. For now, it won’t
happen.
Jane’s suggests that the Royal Navy,
as a consequence, will lose the embarked UAS capability, but given the
ridiculously small sums of money required, I believe the Scan Eagle deal will end
up renewed before it expires next year.
The other UAS programme the Royal
Navy wanted to launch is the Joint Mini UAS, and its target is procuring a more
capable replacement for Desert Hawk. Obviously, the hope is to have a single
programme run in common with the Army. It is currently impossible to say
whether this has been able to secure some funding or not. Desert Hawk III has received an upgrade giving it
digital communications and has seen its operational life extended 6 years, out
to 2021. Further upgrades are being evaluated but are not under contract: LM
offers a "3.1" upgrade package that extends endurance from a maximum
of 90 to 150 minutes; fully waterproofs the drone and replaces the current
interchangeable sensors with an integrated electro-optic, infrared and laser
illuminator payload, so that all functions are available at the same time.
This upgrade might be a cheap solution for making the DH III the mini-UAV of choice well into the 2020s, but the Army and the Royal Marines are already investigating a replacement. Plextek is working to develop a miniaturized solution for Sense and Avoid and also a mini radar sensor that could fit within a mini-UAV fit to replace DH.
Sense and Avoid would make it much safer to employ low-flying UAVs in areas where helicopter movements are also present: the British Army has had near miss events which have caused some worry.
This upgrade might be a cheap solution for making the DH III the mini-UAV of choice well into the 2020s, but the Army and the Royal Marines are already investigating a replacement. Plextek is working to develop a miniaturized solution for Sense and Avoid and also a mini radar sensor that could fit within a mini-UAV fit to replace DH.
Sense and Avoid would make it much safer to employ low-flying UAVs in areas where helicopter movements are also present: the British Army has had near miss events which have caused some worry.
Potentially good news for the Royal Navy come,
indirectly, from the Apache CSP deal going to Boeing, as Leonardo Helicopters (ex
AgustaWestland) has received, as a consolation prize, MOD reassurances about
funding for the development of an unmanned helicopter. The Royal Navy wants a
Rotary Wing UAS in the 2020s, so at least on this front it might have managed
to move an important step forwards.
Frigates despair
Waiting for the Shipbuilding Strategy due in October, I
can’t help but despair at the direction that frigate programmes have taken in
the Royal Navy. The General Purpose Frigate programme launched by the SDSR 2015
is apparently aiming extremely low, and the lack of ASW usefulness is a real
concern when looking at these frigates that seem not to have a clear role other
than existing.
BMT is offering its Venator 110 design, and now BAE
has revealed two proposal of its own, Avenger and Cutlass. The first,
incredibly underwhelming and ugly, is a stretched River Batch 2 turned into a
111 meters “frigate” with some CAMM missiles and a 127mm gun.
Cutlass is little better, being a 117 meters extended
Khareef corvette, in itself a development of the River design.
I can only be deeply critical regarding the whole
affair. Again, we are back to the actual question:
what is this "frigate" actually good for? And the answer always is,
not much. Everything it can do comes with a load of caveats and assumptions
about enemy capabilities and about other ships accompanying.
This is
looking, to me, as the very definition of waste of money, especially considering
that the Royal Navy is going to have some 6 OPVs (and it could easily have more
by life-extending River Batch 1s) and, soon enough, it'll have to start
thinking about what platform to build to replace the minesweepers. And that one will probably emerge as a platform good enough at a range of constabulary tasks as
well.
Suddenly, the Royal Navy goes from having pretty much no low tier at all to having 3 different low tier classes, paid by opening an even bigger hole in Escort numbers. In my opinion this is abject failure in planning and strategic coherence. The result of having few ideas, and well confused, shaped by eternal budget-driven short termism. The same short termism that, elsewhere, generated air refueling tankers with drogues and strategic platforms (the receivers) fitted with receptacles.
Suddenly, the Royal Navy goes from having pretty much no low tier at all to having 3 different low tier classes, paid by opening an even bigger hole in Escort numbers. In my opinion this is abject failure in planning and strategic coherence. The result of having few ideas, and well confused, shaped by eternal budget-driven short termism. The same short termism that, elsewhere, generated air refueling tankers with drogues and strategic platforms (the receivers) fitted with receptacles.
Escort ships must be good at
escorting. In a world of ever faster and deadlier missiles, of drones and of
resurgent submarine fleets, Avenger and Cutlass have little to offer. Even Type
26 itself is concerning. I’ve been worried all along by the propulsion architecture
chosen, which I fear will become a major issue in the future when new systems
will require more power. The feeling is that the Type 45 propulsion fuck up
resulted in a full and hasty retreat from integrated fully electric propulsion,
and the fear is that this retreat might be, in a non distant future, cursed
bitterly.
I’m increasingly worried about
the capabilities that the Type 26 will actually deliver. With no programmes
evident about replacing Harpoon and with no real talk about ASROC-like weapons
for ASW, nor about cruise missiles for land attack, the question of what will
arm Type 26 becomes more and more pressing. Someone is bound to ask, at some
point, if the MK41 modules at the front are meant to contain something, and if
the Royal Navy hasn’t planned ahead for it, the only possible outcome is “Fitted
For But Not With” MK41. It is a movie we already saw.
But if that happens, and it is
looking more and more likely, Type 26 will be an extremely underwhelming ship,
without ASuW (there are no provision for above-deck canisters), without torpedo
tubes, without ASROC, without anything other than CAMM and 127mm gun.
The ship will have become uselessly expensive just to incorporate empty space "for future growth", while lagging badly in every area for at least the first part of its service life.
The ship will have become uselessly expensive just to incorporate empty space "for future growth", while lagging badly in every area for at least the first part of its service life.
If the Royal Navy ends up with such
a planning failure, we will no longer have doubts about why admirals no longer make it
into the Chief of Defence Staff chair. It is a bitterly painful state of affairs, because the Type 26 was the programme that had to save the Royal Navy, and might instead be, along with GPFF, the one that sinks its credibility for good.
It is my firm opinion that it is time to think long and hard at how to make surface combat ships (bothering with the terms "frigate", "destroyer" and "cruiser" has been steadily losing relevance) actually good at something again.
They are increasingly vulnerable to air attacks and to submarines, yet little is being done to improve the situation. The US Navy is at least trying, retrofitting its destroyers for ASW, developing the Continuous Active Sonar and investing on the rail gun, on networked, cooperative engagement of air threats etcetera, while the Royal Navy seems to be almost dead in the water.
I've written a lot about my views regarding surface warships for the future, and i recommend reading the two main articles, which i hope will contribute to encouraging discussion and innovation.
Are escort ships still up to task?
What is a Type 31?
MARS Fleet Solid Support
The MOD confirms that the Heavy RAS demonstrator from Rolls Royce proved that the 5 tons RAS is achievable. This is a key future feature for FSS, enabling it to transfer large paylods to the aircraft carriers, much quicker. It will also enable the new supply ships to resupply the carriers with spare F-135 engines for the F-35s.
The MOD has begun talking with industry about the 3 FSS ships, which should be delivered "around the middle of the 2020s". The current ships Fort Rosalie, Fort Austin and For Victoria are expected to pay off beginning in 2023, but we have to assume there could be a further slip to the right to adjust the timeframe.
The requirement has been officially classed as "non warlike", meaning that foreign shipyards will be able to present their offers, making it quite likely that, just like the Tide tankers, the FSSs will be built abroad.
It is my firm opinion that it is time to think long and hard at how to make surface combat ships (bothering with the terms "frigate", "destroyer" and "cruiser" has been steadily losing relevance) actually good at something again.
They are increasingly vulnerable to air attacks and to submarines, yet little is being done to improve the situation. The US Navy is at least trying, retrofitting its destroyers for ASW, developing the Continuous Active Sonar and investing on the rail gun, on networked, cooperative engagement of air threats etcetera, while the Royal Navy seems to be almost dead in the water.
I've written a lot about my views regarding surface warships for the future, and i recommend reading the two main articles, which i hope will contribute to encouraging discussion and innovation.
Are escort ships still up to task?
What is a Type 31?
MARS Fleet Solid Support
The MOD confirms that the Heavy RAS demonstrator from Rolls Royce proved that the 5 tons RAS is achievable. This is a key future feature for FSS, enabling it to transfer large paylods to the aircraft carriers, much quicker. It will also enable the new supply ships to resupply the carriers with spare F-135 engines for the F-35s.
The MOD has begun talking with industry about the 3 FSS ships, which should be delivered "around the middle of the 2020s". The current ships Fort Rosalie, Fort Austin and For Victoria are expected to pay off beginning in 2023, but we have to assume there could be a further slip to the right to adjust the timeframe.
The requirement has been officially classed as "non warlike", meaning that foreign shipyards will be able to present their offers, making it quite likely that, just like the Tide tankers, the FSSs will be built abroad.
Enjoyed reading this Gabriele, thank you.
ReplyDeleteConcerning Strike Brigades - Why do they not just group the LPM Foxhound Battalions together, 3 to each Brigade, along with supporting vehicles like Husky, Panther, and buy a new wheeled recc vehicle like the French AMX10 for the 2 Light Cavalry Regiments, and give the existing Jackal/Coyote vehicles in the light cavalry to the recc elements of the LPM Battalions, replacing WMIK. This keeps the Ajax where it belongs in the armoured brigades and saves the recc elements of our warrior and Challenger units.
This would improve the pretty useless 7th and 51st Brigades, both famous names, while preserving the reaction force! This whole Strike Brigades concept seems nothing but a stealth cut to me if they are messing with the Armoured Brigades to achieve it.
Daniele,
DeleteYou have hit the nail right on the head.
Add up the units that would have been in the 3 armoured brigades, now add up the units that are in the 2 armoured and 1 strike brigades.
At least one infantry unit less, maybe three.
Phil (the cynical ex pongo)
One of the most damning conclusions of the Chilcot Report related to sending our armed forces into battle without the proper equipment to defend themselves. Fitting, for example, ships 'for' but not 'with' the equipment needed to defend themselves or to neutralise the enemy is scandalous and to my mind a dereliction of duty.
ReplyDeleteWhen I first started considering these things, some years ago, I had assumed (bought the idea) that the problems faced by the armed forces arose from a combination of lack of funding, political interference and problems within the MOD. Now, while I have no doubt that all of those elements are still important, I have to conclude that, increasingly, the number one problem faced by all three services lies in their leadership tier and their seeming inability to think strategically or indeed coherently either concerning their own service or even more so in a joint manner. Yes it is difficult to forecast the future, even more so in times of political inference and tight budgets, but some of the mistakes and decisions being made defy explanation or understanding - the A to A tankers, the surface fleet in general, artillery, the wildcat helicopter, the armoured vehicle programme in general, force structures in general (particularly in the army) all of them are at least as much the responsibility of the services themselves.... Seemingly our leadership simply can't think in a strategic manner, particularly when compared with the French and the US.
ReplyDeleteThe big problem is that the lack of manpower and money, but still having all these missions and requirements, forces the armed forces into making all these dumb decisions. All to do things like preserve capbadges, have ship and squadron numbers. But all it does is create a hollow Army, Royal Air Force and Royal Navy.
DeleteQuite, but given the budgetary constraints we are merely shifting deck chairs on the Titanic by pretending that we can operate in a high tempo conflict.
DeleteWith 80% and upwards of casualties in high intensity conflict surely it merely becomes a logical matter of bringing artillery bear in the most efficient way possible?
11 vulnerable AS90s could dump 75 tonnes or so of ordinance roughly on target in just over an hour if the time and space to stockpile ammo was available, the same could be done by a single destroyer with an AGS 155 from miles off the coast.
The most significant problem is the surface combattant fleet; in addition to the T$% propulsion issues, excessive ongoing risk in the T"^ programme we now have the RN seemingly about to try and procure a ship (Type 31) that is virtually useless in the context of the emerging threat environment (Russian naval resurgence) and much of the rest of the threat profile the RN faces. The surface fleet future looks almost catastrophic.
ReplyDeleteDepressing to read that the T26 looks to be going the same way as the T45. As far as the T31 is concerned, it should be cancelled. The RN has no need for an expensive patrol frigate that has no real capabilities to offer and the OPVs can cover the low-level tasks.
ReplyDeleteThe Cutlass class grows on you, and I'd say a purchase of 3 ahead of any T26 order would alleviate some of the pressures from the fleet, by covering the low threat standing commitments for WIGS, FIGS and APT(S) from Gib. Sure its really a patrol sloop, but as has been argued before the higher you go the more it costs ornturns into a T26. A delayed start of a few years would give time to complete the T26 negotiations and ensure a design that is not a turkey.
ReplyDeleteWith Brexit I'd also keep the 3 Batch 1 Rivers, with the 3 Batch 2 Rivers will be enough to patrol the UK EEZ for terrorists and illegal fishermen.
I actually think the Avenger and Cutlass designs are pretty good looking but i completely agree that without any sonar, anti-submarine or anti-surface capability they won't be cut out for much more than flying the flag and chasing speedboats in various backwaters. We now have plenty OPV's on the way (albeit expensive and with limited aviation facilities) and what the RN really needs is a fleet of proper anti-submarine frigates to slot into the future carrier-group and counter a resurgent Russian Navy.
ReplyDeleteSadly until we understand just how/why the supposedly cheap and conservative T26 design has been messed up so spectacularly before the first steel has even been cut we are doomed to keep making the same mistakes.
I say we when i really mean BAE and the MoD who have seemingly lost the plot in terms of design and cost control.
Really hope the upcoming shipbuilding strategy offers some answers and offers stability for the road ahead.
I broadly agree and keep asking myself if the huge numbers of senior officers in the armed forces are able to think beyond the immediate.
DeleteWe seem to have reached a situation in the Army pre Haldane and the navy pre Fisher.
I really can't comment on the RAF.
Maybe the trouble stems from the lack of long serving and knowledgeable political leadership; certainly so under Labour.
As Beatty exclaimed to his flag captain Chatfield at Jutland-'There is something wrong with our ships and something wrong with our system'.
Those new Rivers can do in flight refueling for helicopters..
DeleteAnd the MRA4 program must have left at least 4 sets of equipment lying around disused in an MoD shed. So, bit of a reach here but buy a few Airlander 10s, fit the kit from the MRA4s and use them in combination with the Rivers as MPAs around our coasts.
Frankly the Avenger and Cutlass designs don't really offer that much in comparison to a River. The RN seems to have given up on NGFS though there is still 148 bty, just about all they offer on top of the Rivers.
With 34 Regular Battalions could the Army be organised as:
ReplyDelete3 Brigade - Royal Marines x 3 Battalions
16 Brigade - 2 x Para/1 x Guard Battalion
1/12/20 Armour - 1 x Armoured Battalion/2 x Mechanised Infantry
My change would be:
3 x Strike Brigades (for Arguments sake say 30/31/32) each of 3 Battalions on MIV (Patria with Cannon and Missile)
That leaves 9 Battalions organised in 3 further lights brigades (each rotating to Falklands/Gibraltar and Cypress for 12 months (ratio being 2 battalions on Cypress and the last battalion split between Falklands and Gibraltar at 1/3 and 2/3.
That leaves 4 Guard battalions (2 on Public duty and 2 in Northern Ireland). An independent company could be deployed to Belize. The Guards would rotate in an out of the light Brigades to give them deployment exposure.
That's enough for 3 Divisions (1 UK Armoured/3 UK Mechanised - strike/5 UK Light.
The Reserves (currently 14 battalions) could be aligned with these.
Gaby
ReplyDeleteI was interested in one of your tweets concerning news that Rheinmetall has submitted a comprehensive offer to upgrade and enhance the British Army’s Challenger 2 Main Battle Tank.
In their article, Rheinmetall states that it is concerned with solving “not only the obsolescence issues of the Challenger 2 but to also cost effectively enhance the capabilities of the MBT”. They say that their solution could “integrate either the existing 120mm L30 rifled gun or their proven 120mm L55 smooth bore system that is in service with the German Army and can fire the latest generation kinetic energy rounds and their unique 120mm air-burst ammunition.”
Do you reckon that means that they could integrate the smoothbore gun, which would fire very advanced ammunition without replacing the Challenger turret or would it necessitate a turret change? I think the British Army has experimented with fitting the German gun before and not too successfully.
Incidentally good news that there is at least some hope on replacing RFA Diligence.
Hope you pick this message up!
Hey Mike,
Deletei was surprised by Rheinmetall's statement, and now i'm hoping to hear some more details about it, because if they have a workable plan for swapping the gun, that would be simply great.
The problem, notoriously, is that swapping the gun is really easy, but adapting the ammunition storage spaces is pretty much impossible. CR2 uses ammunition broken down in two pieces, so that the storage bins are way too short for one-piece rounds. And stowing the explosive parts below the turret ring will no longer be an option with the L55, so that requires ammo storage spaces to be suitably protected. This is what killed the gun-swap project the first time. If they have put together a workable plan, it would be fantastic.
As for RFA Diligence, i hope the RN will pick up a replacement, but i don't know how much i can believe in it. I remain, sadly, skeptical.
Gaby
DeleteMany thanks for your knowledgeable reply. As you say, if Rheinmetall have found a way round the problem that would be tremendous. Replacing the whole turret would be highly expensive.
I think you are right to be sceptical about a replacement for RFA Diligence. It's a shame because I think it was you who said they could take up a commercial/merchant ship for something like £50 million.
One last question. The newspaper reports suggesting that the SAS were using the XM 25 "Punisher" in Iraq might be true. If so, could its use be spread to to the mainstream British Army? I have read that they are looking for a stand-alone grenade launcher. Is the weapon progressing satisfactorily and therefore likely to enter service with the American Army, for instance?
The US army intends to adopt it; the british army, we'll see what it does. Ideas seem confused in the so called "optimizatioN" of platoon weaponry...
Delete