Wednesday, May 28, 2014

State of the Royal Navy: a roundup - Part 1



Type 45

Some good news from the Type 45s front. All ships appear to have received their Phalanx fit, even HMS Duncan, the last vessel to enter service, which sported them in her recent visit to Oslo for the 200 years of the norwegian navy.
As we have known from MOD words since last year, Harpoon missile fit is also on the way for four of the six ships. It is not exactly clear when the missiles will take their place on board, but the Royal Navy's website itself is confirming that HMS Duncan is going to be the first in class getting the system. Unconfirmed reports suggest that Daring, Dragon and Diamond will be the other three. It remains unclear if the other two ships in the class are going to be cut out entirely, or if they will be fitted with the launchers infrastructure, wiring and software, allowing the missile fit itself to be moved from vessel to vessel to ensure the deployed ships have the capability.
The MOD said that additional equipment would be purchased to enable the integration of Harpoon on Type 45 (in addition to the kit that is recovered from the four decommissioned Type 22 Batch 3 frigates) but it is not clear if it is needed for the four ships, or to prepare the other two.
If all vessels get the infrastructure and system integration, swapping the missile fit from one to another is not going to be an issue; but unfortunately i'm inclined to read it as having two vessels which will flat-out not get the capability.
It is also not clear when the missile fit will appear. HMS Duncan was seen in port last march with a white tent covering what was almost certainly work related to getting the Harpoon infrastructure in; but on her subsequent sorties to sea, she still does not sport the missiles.

HMS Duncan in Portsmouth, back in March, with tarpaulin covering the Harpoon area. It is reasonable to assume she underwent some fitting out related to the missile fit, but the job isn't finished yet. Photo by Chris Argles. Thank you for letting me use the image!

Seen in Oslo in May 2014, HMS Duncan has gained Phalanx, but is still missing Harpoon, in a Royal Navy photo

HMS Defender has made progress towards full capability by receiving her own Phalanx fit and by firing Sea Viper for the first time on May 15.

Those who follow me on Twitter already know that i've been doing my best to track the Anti-Ballistic Missile tests undergone by HMS Daring in her long deployment in the Pacific. A while ago i had concluded, thanks to documents of the US Missile Defense Agency, that she had been part of
Flight Test Operational-01 (FTO-01), a US BMD System operational test executed at the Reagan Test Site/Kwajalein Atoll in the Marshall Islands.
Since then, an interesting Jane's article has confirmed that i was right in my reconstruction of the events. The results of HMS Daring's work with the modified SAMPSON radar have been good enough that the MOD has provided additional funding to continue with the ABM development program. This is a welcome development, even though so far there continues to be no plan for the eventual roll out of ABM capability to the Type 45 fleet, nor any plan to provide the ships with anti-ballistic missiles. 
The new phase of development should culminate in another ABM test in 2015. The target is to better integrate the ABM radar functionality into the ship's combat system, and add better interoperability with US ABM assets by introducing the necessary data link format. 
The 2013 test used an ABM software functionality that was separated from the ship's mission system. This required the effective "shut off" of the normal Anti Air Warfare capability of HMS Daring, which slaved its main radar to the sole ABM task instead. 
The aim for 2015 is to demonstrate an integrated ABM function running alongside the AAW mode. This paves the way for a "full spectrum" air defence and anti ballistic capability comparable to the latest american AEGIS Baseline 9 combat system; an ambitious target. 

In early 2016 the Type 45 fleet will also finally begin to receive the fully integrated Electronic Chart Precise Integrated Navigation System, the key component of the Warship Electronic Chart Display and Information System (WECDIS) navigation capability.
WECDIS is a fleet-wide program which is delivering electronic mapping and navigation to the fleet, including to submarines. 



Type 26 

Although still unconfirmed, according to Jane's the MOD is about to select the BAE MK45 Mod 4 gun as the artillery piece for the Maritime Indirect Fire System program, a branch of the wider Type 26 frigate enterprise. This would mean defeat for the Oto Melara / Babcock team, offering the 127/64 Lightweight, which was earlier seen as the favorite. 
The Lightweight is a more modern artillery piece, offering a much higher rate of fire (over 30 rounds per minute versus 20 plus) and a wholly automated high capacity ammunition magazine. Both BAE and Oto Melara can also offer guided long-range ammunition, respectively the Standard Guided Projectile and the VULCANO ammunition family. These follow very different design phylosophies, with SGP using rocket propulsion to extend the range of a full-width 127mm shell, while VULCANO uses a sabot-discarding, slim dart which exploits aerodynamics to reach long distances, at the expense of a smaller payload. Details of the two guns and of their ammunition is inside an earlier article.

In addition, British Forces News has visited the BAE design centre, and saw the virtual reality 3D design work ongoing for the Type 26 frigate. Observing the design work, a couple of things caught my attention: the new warship is possibly going to have a mission centre aft of the bridge, with windows looking out directly over the sides of the vessel, and possibly even facing aft, to give a greater and more immediate situational awareness. 
These 360° degrees bridges are becoming more common in warship design. The Holland class OPVs use the COBRA (COmmand BRidge Aft) arrangement; while other vessels have similar conceptual solutions, such as the DCNS Androit OPVs, and the still in design PAM multi-role warships for the italian navy.  
There is no way to confirm, at the moment, whether my suspect is correct or not, but windows definitely seems to have appeared aft of the bridge, suggesting a COBRA-like arrangement. 


A long row of new windows has appeared aft of the bridge, right beneath the sensors mast. The funnel mast also seems to have been redesigned and split into two masts of differing heights. 
The COBRA used on the Holland OPVs offers a mission control centre right behind the bridge. Armored windows ensure direct view of the bridge itself (see photo) as well as of the sides of the vessel. 
Panoramic view of the COBRA centre, with windows giving a view on the bridge and on the sides of the vessel. Might the Type 26 gain a similar arrangement?


The bridge itself seems virtually identical to the Type 45's one. The images shown do not allow me to say whether there are windows between the bridge and the supposed mission control area aft of it, like in the COBRA arrangement.


The graphic of the design being refined by BAE also suggests that the funnel mast has changed, splitting into two masts of different height. 



It will be interesting to see how the mast area is eventually reconfigured, and if it has any impact on the disposition of the pole masts and related communications equipment; on sensors and eventually even on weapons capability. The aft CAMM launchers apparently are still there, in the low mast aft of the funnel area, but maybe the new arrangement opens up space for anti-ship missile launchers?

The monolithic funnel mast as last showcased, at DSEI last year, with the CAMM missile cells. The more recent graphic suggests a split mast, with the aft half rising higher up (apparently almost to the same height of the SCOT 5 satcom radomes on the mast). Might we be looking at a new base for sensors or a relocated pole mast? 


In the design as last showcased, the Type 26 appears to have no space available for the fitting of the traditional quadruple missile launchers employed by Harpoon, NSM, Exocet, Teseo and other missiles. This could be seen as both a weakness in regard to exportability (those missile systems remain the most prevalent on the market) and a risk to the Royal Nayy's own anti-ship missile capability in the future, as there still isn't a truly defined plan to acquire a vertical launch weapon to replace the old Harpoon. The redesign could also address this aspect, possibly.



The Type 26 program should get the go ahead by the end of the year, probably with the aim to sign a contract for the first 8 frigates, leaving the other five for another day. 
Among the hurdles to be overcome, we have to include the referendum that will decide the future of Scotland. Until the result is known, the shipbuilding programs will be somewhat restrained, including the final go away for the BAE's plan of redevelopment of the shipyards on the Clyde. The preferred option sees a 200 million upgrade to the Scotstoun facilities, to create a single, fully capable yard, with the closure of Govan and the transfer of the manpower. There is also, formally, an alternative that sees both shipyard retained, and given a more limited uplift. The ship building process split on two sites, however, is less efficient. Finally, there's the "doomsday" scenario that sees both these ideas junked, in the quest for uplifting the capacity of one of the shipyards south of the border instead, in the case Scotland walks away. Something i dearly hope does not happen, as it would bring nothing good, to no one.

 




 
Submarines

HMS Tireless is about to leave service, after having its life extended (it was planned it would decommission already last year) and after completing another long deployment which gained great media visibility when it was sent searching for the lost MH370 airplane. 
HMS Artful, the third of the Astute class submarines, has finally entered the water, many months later than originally planned. In general, the delays of the Astute class sure have kept the Royal Navy worried for a long time, and caused quite a bit of pressure. 

Artful is the first in class fitted with the Common Combat System (CCS), which uses common consoles, electronics cabinets, and commercial off-the-shelf hardware and software to create a shared computer environment. The CCS is the result of a Royal Navy initiative to streamline and future proof the fleet's combat systems, to develop more open system architectures that are more cost-effective to maintain and easier to update.


The next submarine, Audacious, will be launched incorporating further improvements. such as the Naval Extremely / Super High Frequency Satcom terminal (NEST) and a variety of enhancements grouped under the Astute Capability Sustainment Programme. 
NEST has seen the installation of a new antenna and related equipment at the Colerne satellite ground station in Wiltshire. This new equipment enables Super High Frequency communications using the british Skynet 5 satellite constellation, or Advanced Extremely High Frequency communications using the american AEHF satellite constellation.

The Rafael TORBUSTER advanced countermeasures system, which uses decoy which combine seduction and hard-kill capability, has been proposed as part of the Astute CSP by a team made up by BAE, Babcock and Rafael, but we might never get told whether it is being installed or not.When it comes to submarines, information is always sparse. 
Full new Communication and Radar Electronic Support Measures (CESM and RESM) capability has also been funded as baseline fit from Boat 4 onwards. 

The Spearfish heavyweight torpedo upgrade programme is also underway. The program includes the replacement of the two different fuels employed by the torpedo with a single one; the replacement of the warhead with a new one, compliant with Insensitive Munition rules; the digitalisation of the weapon; and a new fiber optic guide fibre replacing the current copper/cadmium wire, removing the delays in communication between the torpedo and the submarine. The end result will be almost a new weapon, with much greater capability and greater safety. Again, the details on the state of the Spearfish upgrade program are under wraps, but there has been a delay in the signature of contracts for the next phase of the work, which means delays. 

Looking ahead, to the delivery of the next Astutes and further away to the Successor SSBNs, the MOD and BAE have given green light to a 300 million project for the upgrade of the shipyard facilities in Barrow.  




The future could also include ultra-accurate navigation, completely independent from vulnerable GPS signals, thanks to a science development project ongoing for quantum positioning technology.



New OPVs

The contract for the delivery of three new OPVs should be signed soon. Little is known about these vessels, other than they will be derived from the 90m OPV design mostly known as Amazonas class, due to the ships of this type having been purchased by Brazil.
The new OPVs will have a flight deck compatible with the Merlin helicopter. What's not at all clear is the fate of the OPVs of the royal navy, as shortage of money and manpower might make these new vessels the replacements for the still young River-class. Even though the MOD has just purchased, for 39 millions, these vessels which have been operated for years under a leasing agreement.

I've already expressed my opinion that such a decision would be an inexcusable waste of money, time and good ships. While i fully understand the rationale of keeping the shipyards working to bridge the gap between the carriers and the Type 26 frigates, in order to keep the production line "hot" and in order to retain manpower and expertis, i think that withdrawing the Rivers would be a grave mistake.
The new OPVs will be extremely welcome and useful if they are kept in addition to the Rivers, not in their place.
The Rivers will be barely around 14 years old when the first new ship is delivered, in 2017, and the Royal Navy has a clear need for deployable hulls. The new OPVs, with their greater sizes and capability (including helicopter) can and should be used away from home, to relieve the frigates of some of their tasks (Caribbean, but also counter-piracy, for example), while the River continue to do what they have done well for years.

The government has right in these days published its Maritime Security strategy. The document, while being of some interest, hardly deserves the praise it received from several commenters. Moreover, the supposed "strategy" is written out in a deliberately ambivalent, vague way, especially when it comes to the new OPVs: mentioned several times in the document, they are described as a "further improvement" to the UK's maritime security capability, but not once there is a clear statement of their fate, and that of the Rivers. The official line is that the decision is left for the next SDSR. Of course.
The document has been written in such a way to allow the government to bin the Rivers and still describe the situation as an "improvement" because of the greater capabilities of the new vessels, regardless of the fact that, observing historical trends in the use of the Rivers, it is safe to say that such additional capabilities would be hardly be needed, and will only sparsely be exploited.

The hope can only be that, thanks to the very modest cost in money and manpower, the OPVs gain points in the SDSR.


Carrier Enabled Power Projection 

With HMS Queen Elizabeth to be named by the queen on July 4, and the manufacture of HMS Prince of Wales currently significantly ahead of schedule, the building of the carriers is progressing well. The program costs have been re-agreed, hopefully for the last time, and the MOD is planning ahead to reach the SDSR 2015 with a full set of options for the way ahead for CEPP. In particular, the MOD is coming up with plans for the second carrier, as well as for the vital MARS Fleet Solid Support capability, which has to deliver the ships which will replace the Fort class vessels in the 2020s.

CEPP also includes a dependency program for the delivery of amphibious capability via the carriers, a requirement made unescapable by the impossibility to fund a dedicate replacement for HMS Ocean.
The carrier includes design features such as wide assault routes and accommodation for a 250-strong reinforced Marines company, which can be expanded further depending on the composition of the air wing. Less jets means more Marines and helicopters. Deck manoeuvers, and even deck layout, are being thought out to accommodate the amphibious requirement, including concurrent jet and helicopter operations. It is possible that the deck layout selected will include 10 spots for medium helicopters operations.

In a very welcome move, the MOD has also moved to substantially close the unacceptable gap in AEW coverage, by keeping 7 Sea King ASaC in service all the way to 2018, and by speeding up the CROWSNEST program by 18 months, with the aim of having the first AEW capability on Merlin HM2 in 2018, in time to nearly completely avoid the gap.


Fleet Air Arm  

As said above, even as the Sea Kings of all other variants are withdrawn from service in 2016 as planned, 7 MK7 ASaC will be kept flying with 849 NAS up into the second half of 2018. By then, it is hoped that the initial capability of the CROWSNEST radar package for the Merlin HM2 will have been achieved, substantially closing the dangerous, unacceptable AEW gap which would have lasted for a good four years or more according to the initial plan.

As a way to prepare to the return of fixed wing naval aviation when 809 NAS will reform on F-35B, the Fleet Air Arm has taken back control of Fleet Requirements and Air Direction Unit (FRADU) from private contractor Serco. The squadron, equipped with 14 Hawk T1s, was recommissioned in Culdrose on June 6, 2013 as 736 NAS.


736 NAS is an extremely busy squadron, which has inherited all the tasks of FRADU.
Its role is serving as Maritime Aggressor Squadron, and is best known for providing threat simulation to warships conducting OST in the South Coast Exercise Areas. The Hawks, with the help of Falcon 20 aircraft loaded with towed targets and EW pods, provided by the contractor Cobham, train the royal navy in defence against air attacks.
736 NAS also delivers intercept training to the RN School of Fighter Control at Yeovilton, Close Air Support (CAS) training to 3 Cdo Bde as well as Army units, and Affiliation training to Rotary Wing Squadrons at both Culdrose and Yeovilton. It is a good place, in other words, for the Royal Navy pilots to work their way up to the rebirth of naval fixed wing aviation. 

FRADU in action, with Hawk and Falcon 20 jets, the latters equipped with a variety of EW system pods

The Fleet Air Arm has finalised its plan for the transition from Lynx MK8 to Wildcat HMA2, which will include the return of 825 NAS, which will reform out of the merge of 700W Nas and 702 NAS as the training squadron moves on from Lynx to Wildcat. 



825 NAS will be commissioned in september this year, to deliver training for the Wildcat and to form the first four ship flights. 
815 NAS will begin to convert to Wildcat from the second half of 2015. The transition will take time, and Lynx helicopters will continue to provide their service all the way up to their OSD, planned for 31 March 2017. 
815 NAS, once fully converted, will line 12 single-manned Flights at readiness for deployed operations worldwide and 2 double-manned MCT Flights at very high readiness in the UK.

One problem remains for Wildcat: the big delay in the FASGW program which has to deliver the two missiles it will use in its maritime attack role. They are not expected to be available before 2020, which means a big gap is taking shape as the Lynx force draws down and, with the Lynx, the Sea Skua missile does progressively vanish as well. 


Separately, in the Commando Helicopter Force, 847 NAS is converting to Wildcat as well, but the squadron uses the Wildcat AH1, the same variant employed by the Army, in support of the Royal Marines. 847 NAS will be the first operational Wildcat squadron.

Another transition is due to take place in the CHF, with the Sea King HC4 being replaced by the ex-RAF Merlin HC3/3A, later to become HC4 as they are fully upgraded and navalised.
While Fleet Air Arm crews have been training for a long time and the transfer of the helicopters to the Navy is underway, the first bit of naval capability will only arrive between late 2015 and early 2016, as the first 7 Merlin are delivered in interim, Phase 1 navalisation including folding rotor head, lash down points and other minor changes. These helicopters (HC3i) will bridge the gap forming as the Sea King HC4 bows out of service, replaced by helicopters which, in their current form, are unsuitable for shipboard operations.

848 NAS, the training unit for Sea King HC4, stood down in december 2013 after delivering the last training course. 846 disbanded in March 2014, leaving Sea King to move on to the Merlin. The squadron will reform in September 2014, while the RAF Merlin squadron 78 will disband as the helicopters are handed over.
845 NAS continues to serve the Marines, with a mere 11 Sea King HC4 left in service. The squadron will reform with Merlin in August 2015, and sometime in the same year the second and last RAF Merlin squadron (28 Sqn) will disband.
It does not seem to be planned to reform 848 NAS: training will probably be delivered from within the two frontline squadrons. The total number of crews in the force will drop from 43 to 37, with all of them expected to be trained come 2016.

For the disbanding RAF Squadrons, there's a little ray of hope, as one of them might stand up again with Chinook as the new HC6 arrive, but this is not confirmed at the moment.

25 Merlin helicopters will undergo upgrade and navalisation (Phase 2) including the seven interim helicopters. The full program of changes includes electric folding tail, folding rotor head, lash down points, fast rope kit, a cockpit upgrade like that of the naval HM2 helicopters, an integrated digital map system, improved CHF-specific communication systems and uplifted integrated defensive aids suite, including Generation 3 Common Missile Warning System, which actually ads the capability to locate the source of small arms and RPG fire as well.
The first fully reworked helicopter, to be known as HC4 / 4A, will be delivered in late 2017, and the deliveries won't be completed before march 2022.



Friday, January 11, 2013

Gaps, gaps, gaps - part 2



Part 1 of this report: Gaps, Gaps, Gaps


Next in line is the FRES SV vehicle family. Unfortunately, the NAO report covers a period that ends before the most interesting developments. Following confirmation of the enduring requirement for FRES SV at the completition of the SDSR, and indeed following the army restructuring program (Army 2020), the number of vehicles to be purchased and timings have all changed.
Entry into service will happen at least 9 months later than originally planned. The date is not disclosed, but we are possibly looking at 2018, if not later. I've read that CVR(T) vehicles will not be entirely gone before 2026.

An option that could be given the go ahead in the immediate future would however partly compensate the delay to entry in service by bringing forwards development and demonstration of the RECCE Block 2 group of vehicle variants.
The FRES SV has been broken down into multiple parts, all with their own decision Gates. So far, activity has focused on RECCE Block 1 (Scout vehicle, Armoured Personnel Carrier, Repair, Recovery and Common Base Platform) but the Block 2 could now be added to the ongoing activity, to demonstrate Ambulance, Command Post and Engineer Recce variants.
Part of the Block 2 should also be the Joint Fires direction vehicle, destined to carry a full six-man Fire Support Team of the Royal Artillery, with full equipment for the direction, under-armor or dismounted, of mortar, artillery and air attacks.

A RECCE Block 3 is also envisaged for the future, but budget uncertainty makes me be particularly careful about these future, as yet uncommitted to parts of the program. Bringing forwards demonstration of Block 2, to include the vehicle variants it covers into the Initial Operating Capability would be a very welcome move, as it would greatly increase the chances for the Army to actually get the vehicles it needs.

The Type 45 destroyers are now going strong, and the program has achieved a very positive in year net cost variation of -108 millions, which have been handed back for use elsewhere in the equipment programme. Reportedly, this year we'll see up to four Type 45 fitted with Harpoon missiles, presumably coming from the retired Type 22 frigates, but the NAO does not speak about it. Major improvements in Combat System software and communications (SATURN has been fitted) are reported.

The Typhoon Future Capability Program is, as always, a source of misery. While the Typhoon program registers a positive result, with a cost reduction of 69 millions, the Future Capability Program 1 for introduction of advanced Air-Ground features reports a 22 million cost increase (to 441 million) and, more importantly, a massive 18 months delay, to December 2013, which also affect the Meteor as we have seen before.

A combination of technical complexity, Partner Nation disagreement on a synthetic training solution and delays in agreement of an international support arrangement have caused the delay.

Anyway, the SDSR has pushed to the right the requirement for Typhoon ground-attack capability to 2015.
Future Capability Program 1 introduces Paveway IV, full functionality of the Litening III targeting pods and other improvements.
Future Capability Program 2 will follow, at some point, hopefully including integration of Storm Shadow and Brimstone.

An Active Electronic Scanned Array voice has made its appearance into the Report, with Initial Investment Decision made in July 2011, but no other detail is provided. The budgeted-for date of entry in service is currently classified.

Regarding the Warrior Capability Sustainment Programme, the NAO reports that the current plan is for the upgrade of 445 vehicles (all variants, including FV514 Artillery Observation Post, but excluding the Battery Command vehicles which appear not to be in use anymore, with a number having been converted in Ambulances by the REME for use in Afghanistan) from an affordable fleet of 565.
The FV514 vehicle is very important to the future of the Royal Artillery. As part of WCSP it is getting mechanical, electric and protection upgrades, but a separate programs will have to be funded at some point to upgrade the fire targeting and direction equipment. I plan to write an article in the near future looking in more detail into the Warrior situation, and more info will be provided there. 

Importantly, the NAO report confirms that the Armored Battlefield Support Vehicle element is not dead, despite having been silent ever since it was made a part of Warrior CSP by the 2005 defence industrial strategy.
The ABSV is described as:

A new variant, replacing obsolescent platforms, that has equal protection and mobility to the core fighting platforms. Armoured Battlefield Support Vehicle is currently in the Concept Phase and is subject to future approval.

The ABSV, also known as "turretless Warrior" is meant to replace a number of FV430 tracked vehicles inside armored infantry battlegroups. Also known earlier as Battle Group Support Vehicle (BGSV) and earlier still as M1P1 (tracked vehicle which was accompanied by the also cancelled M2P2, the 8x8 Boxer vehicle), it has had a complex history to say the least.
At least 3 prototypes were ordered to then Alvis Vickers, and at least one was built and demonstrated. The requirement has varied anywhere between 125 and 300-plus vehicles, with Ambulance, Command Post and General Support variants envisaged.

With how things are evolved over the years, now ABSV and FRES SV Recce Block 2 are kind of in conflict for the same roles, replacing FV430 vehicle variants.
Using turretless Warriors for the roles might cost less than build a wholly new FRES SV, and of course having almost all the battalion using Warrior mechanics is good for logistics, but insertion of technology which is so important for Command and Ambulance vehicles in particular suggest that going for a new, modern FRES variant is desirable.

However, the FRES Engineer/Bridgelayer vehicle has been cancelled, while a Warrior bridgelayer prototype has been showcased in 2011. Since the requirement is still there (some 35 vehicles were envisaged), to support the FRES Scout, ABSV might end up delivering Bridgelayers instead of ambulances, command posts and APCs.
There is also another requirement that has been ignored this far, which is that for a Mortar Carrier replacing the relevant FV430 variant currently in use. As the Mortar Carrier role should not require a too complex modification to the Warrior hull, and since the requirement would be for a low number of vehicles (between 6 and 9 vehicles for each armoured infantry battalion, so around 54 at most) it might make sense to convert surplus Warrior hulls as a low-cost, big-gain program.

This way, FRES SV RECCE Block 2 would replace APCs (not overly complex, but required in significant numbers that Warrior wouldn't be able to cover) and the complex Command, Ambulance, Communications and Engineer Recce / Joint Fires variants, while surplus Warrior hulls could be used for covering the need for Bridgelayers and Mortar Carriers. The numbers are also compatible with what the NAO says, as 565 - 445 gives 120, a number of hulls more than adequate to meet the two requirements i suggest to tackle.

IOC for Warrior CSP remains defined as one Armoured Company equipped and trained collectively at Level 2. Expected in November 2018.

Among the pre-Main Gate programmes appears MARS, which will of course move up into Post-Main Gate in the 2013 report, since the contract has since been awarded for MARS FT.
The NAO report confirms what i had already reported: the procurement of the MARS Fleet Solid Support Ships currently sits on the White Board, waiting to be given the go ahead later in the decade, post SDSR 2015.
Money is planned to be provided from the core budget for assessment phase of Solid Support in the coming budget cycles.

One major, welcome programs in Pre-Main Gate phase is the Network Enabled Airspace Defence and Surveillance (NEADS), which is the Army's effort to modernize the obsolete air defence capability currently available.
A very complex program, it is considered of prioritary importance by the Army since future operations are expected to be conducted in far less permissive environments. NEADS is meant to expand the defence capability to give protection from the whole range of threats: aircrafts, helicopters, cruise missiles and, very importantly, against UAVs and Rocket-Artillery-Mortars. 

Three Increments are planned:

Increment 1 will replace Urgent Operational Requirement equipment with an enduring Counter Rocket Artillery & Mortar automated sense and warn capability from 2015.
This capability is being used in Afghanistan to protect UK bases from rocket artillery and mortar attack. This was provided under Treasury Urgent Operation Requirement Funding. Automatic Sense and Warn capabilities will be brought into the core equipment programme.

Increment 2 will deliver an initial Counter-Unmanned Air Vehicle Capability and replace the existing Counter Rocket Artillery and Mortar intercept capability from 2017 as well as sustain ground-based air defence in the Falkland Islands beyond 2020.


Increment 3 will improve protection against the remainder of the Difficult Air Targets with Full Operating Capability expected in 2027.

The Difficult Air Targets set includes cruise missiles, Unmanned Air Vehicles, Attack Helicopters and Rockets, Artillery and Mortars.
 

Automatic Sense and Warn UOR is an adaptation of the Land Environment Air Picture Provision (LEAPP) equipment program for Afghanistan needs. Another element is JAPPLE. In 2011 i wrote this description, which should still be at least partially valid, even though not much info is available on this kind of systems, for obvious reasons.

The Joint Air Picture Provision of the Land Environment is active in Helmand since 2008. A team of eight, split between Camp Bastion and Lashkar Gah, provide the Joint Helicopter Command and to the Combined Forces HQ a 24-hours complete picture of activity going on in the air, to direct air defence efforts and de-conflict the Joint Helicopter Command routes and missions with the concurrent artillery fire or othe potential threats. In addition to this constant presence, the system also deploys small forward teams with troops where necessary. 

JAPPLE builds on the capability provided by the Automated Sense and Warn system: this was procured as UOR for Afghanistan, and is a combination of software and hardware capable to fuse together information coming from a number of sources, including MAMBA artillery locating/battlefield surveillance radars. Mainly, though, it uses two Giraffe ABM radars. The information is fused and transmitted on the LEAPP C2 network, and alarm of incoming attack is launched via the Waves towers installed in based in Afghanistan. Two Giraffe radars are in Bastion, two in Kandhar.
In the system, at some point, is likely to be integrated also the flow of informations coming from B-ISTAR sensors.
The whole system is currently manned by 5th Regiment RA, with the support of roughly one battery deployed on each Herrick cycle by 16 RA.

LEAPP in itself (Land Environment Air Picture Provision) is a little known but invaluable programme which is going on from a few years, and that allowed the advanced JAPPLE to happen. LEAPP provides near real time correlated air picture for the land environment. It is a combination of control nodes and organic sensors, and a vital software, Bowman data radio-compatible, capable to link and connect all Royal Artillery assets (artillery batteries receive info and feed back into the system the data of their own firing trajectories, so that all things moving in the air can be mapped). LEAPP is deployed at formations Hqs, and provides its air picture to all users via NATO data link 16 and 11.





The report says that the C-RAM interception capability will be replaced in 2017, but please note that the British Army currently has not an in-service C-RAM interception capability. ASW is a detection and warning system only.
In Iraq, the Army deployed, as UOR, a number of american-made Centurion C-RAM trailers, fitted with suitably modified Phalanx CIWS guns taken from the Royal Navy's stock. However, for what i understand that was a temporary solution: Centurion was not deployed to Afghanistan, the trailers have been handed back to the US and the Phalanx guns returned to the Royal Navy.
The "existing" C-RAM capability is virtual, but a C-RAM protection system was promised in SDSR documents. Nice to see that they are sticking to that promise. 

We can assume that  connected to NEADS will also be the replacement for the now retired COBRA counter-artillery radar and for the active MAMBA: the Common Weapon Locating Radar, which should be the ARTHUR Mod C from Saab.
Entry in service should be in 2014 but an order has not yet been finalized.

Some 34 US-made Lightweight Counter Mortar Radar are in use after being procured as UOR. Most of them are in Afghanistan, but a number was also used to provide protection to the Olympic games in London. It's near certain that these precious radars are part of the solutions being brought into Core Budget.

The NAO does not go into such detail in its report, but includes this information:

Approval for the Assessment Phase 1 was given by the MOD Investment Approvals Board in February 2010, and ratified in June 2010 as part of the review by the new coalition Government.
The objective of the Assessment Phase 1 is to establish the most cost effective solution to the Increment 1 requirement and early de-risking activities for Increment 2.
The current approval covers Assessment Phase work required to reach Main Gate 1, which leads to the Demonstration and Manufacture phase for Increment 1 and effectively Increment 2 Initial Gate. The Assessment Phase has been structured into three workstreams as follows:

a. Workstream 0. Initial de-risking activities will identify and address any changes and further lessons learnt as a result of the evolving Land Environment Air Picture Provision and Urgent Operational Requirement projects and current operations. Further work will develop the architecture required to allow the incremental insertion of capability over the project lifecycle. This will also drive coherence into future Urgent Operational Requirement activity and address any scaling issues as a result of the Defence Review.

b. Workstream 1. The work stream will result in the down selection to a single affordable option to be presented at Network Enabled Airspace Defence and Surveillance Main Gate 1 to deliver the Automated Sense and Warn capability. A full option analysis will be undertaken to investigate retaining extant Urgent Operational Requirement and Core Programme components as well as alternative off the shelf solutions.

c. Workstream 2. This work stream will result in the development of a detailed system architecture and associated systems and technical requirements and initial evaluation of potential equipment options. It is planned to de-risk the overall Network Enabled Airspace Defence and Surveillance architecture, by integrating Future Local Area Air Defence Systems (Land) and High Velocity Missile models/ equipments into a representative Network Enabled Airspace Defence and Surveillance system and also undertake an initial assessment of Counter-Rocket Artillery and Mortars effectors.

In 2010, associated with the Strategic Defence and Security Review a number of options were raised to maintain alignment with wider Defence priorities. These were primarily associated with scaling and delivery timings.

An Industry Day was held in November 2010, at which a number of companies were briefed on the programme. Since then industry have been kept informed of developments via a series of newsletters. A series of one to one discussions with industry on Increment 1 is currently being conducted, following the Request for Information for Increment 1.

The NAO notes that, as of March 2012, NEADS activities were on track and making good progress towards the first Main Gate point. The Main Gate expected date, however, is classified and obscured in the report.
Surprisingly, the NAO shows FLAADS(L) as expected to hit IOC or even In-Service date in November 2016: i'm not sure how we should read this passage, however. While FLAADS(M) has long been expected to start replacing Sea Wolf on the Type 23s from 2016, Rapier replacement was expected not to be funded before 2018 at the earliest. I'd be surprised if it had been brought forwards.
Not because it is not needed, but because of budget considerations.

Another program of interest is the already mentioned upgrade to the Spearfish torpedo.

Spearfish is the sole heavyweight torpedo in the UK arsenal and is carried aboard Trafalgar and Vanguard Class submarines. The weapon was introduced into service in 1994 and is the only submarine launched weapon for offensive and defensive operations against ships and other submarines. Spearfish will be deployed in the Astute Class from 2013 and an upgraded Spearfish weapon is the planning assumption for equipping the future Deterrent.

The Spearfish Upgrade project is required to deliver a mid-life upgrade to sustain a credible and safe weapon for future submarine operations. The scope of the project includes digitisation of the weapon, the provision of a new insensitive munition warhead to replace the current ageing warhead, changes to the fuel system and the introduction of a new communications link. The upgrade will address obsolescence and also enable future reductions in through life costs.

Assessment Phase began with a contract assigned to BAE in April 2010, and will be completed in April 2014 with in-water trials. So far, the effort is progressing satisfactorily and on time. The new Insensitive Munition compliant warhead achieved the required level of technological maturity in January 2012 completing successful land based and underwater scale test firings undertaken in Germany and in the UK respectively.

The fibre optic dispensing system evaluation trials in April 2011 proved that the fibre in use was too weak and required replacement with a more ruggerized one. There are no delays to report anyway.

Initial design work to define and develop the interface between the upgraded weapon and the submarine combat system was completed in February 2012. Work is ongoing.

Regarding CEC, the NAO unfortunately confirms that:

Planning Round 2012 has announced United Kingdom Cooperative Engagement Capability Project Delete Option E12AW006S has been taken and is not part of the funded Core Programme. Delete Option also identified £1m to conduct project close down activities in Financial Year12/13.

It is a big loss of capability, in particular for the Type 45 destroyers. It is not clear how this PR12 decision affects the possibility, for the Navy, to resurrect the CEC effort in the coming years.

Particularly unwelcome is this passage:

Once the Sea King leaves service there will be some consequent capability gaps until upgraded Merlin helicopters can take on the tasks of providing helicopter lift from naval vessels to the shore (a two-year gap until April 2018) and providing airborne surveillance and control capabilities for the future aircraft carriers (a potential four‑year gap until 2020). The Department is examining alternative means of closing these capability gaps.

Regarding Crowsnest, the intended replacement for the Sea King MK7 ASaC, we will know more this year, if plans do not change: assessment phase will finally be launched. Avoiding this particular gap is extremely important.
Just as unwelcome is the gap in amphibious support helicopter capability. It is not clear how this must be read: the plan so far has been that in 2016 the Commando Helicopter Force will take over the Merlin HC3/3A, but properly "navalized" HC4-standard airframes were not going to arrived before 2017.
In the disaster, we have to hope that the April 2018 is the new date for conversion to HC4 standard of the Merlins: if the delay is to be intended as total lack of helicopters for CHF for two years due to postponed Merlin transfer, the only sane option is keeping the Sea King going for a little longer. It would be totally irresponsible to do otherwise.



Finally, they have nothing to do with the NAO report, but they are relevant news:

- The british armed forces have selected their new sidearm: it's the 9mm Glock 17 Gen 4 pistol, fitted with Picatinny rail under the barrel. It is lighter than the Browning, the clip holds 17 rounds (vs 13) and it allows much shorter reaction times from draw to firing of a full sequence of 5 rounds.

25.000 pistols have been ordered, at a cost of 9 million. Afghanistan-deployed troops, of course, will get the weapon first. Firearms distributor Viking Arms Limited, of Harrogate, will deliver guns and holsters.

- An UOR has also been financed to procure a number of LSD500 laser surveillance and sniper detection systems from France's CILAS. The systems are for use in base protection in Afghanistan.
I don't question the wisdom of the purchase which i'm sure is made for good reasons, but bases have already the Boomerang III system, while soldiers have seen the UOR for a body-worn or rifle-mounted sniper detection system cancelled last year. I would have preferred to fill the capability gap in terms of wearable/rifle mounted shooter detection system first, to extend the capability to foot patrols away from FOBs and vehicles (a number of vehicles in theatre are fitted with Boomerang III).