Sunday, January 20, 2013

The P8 Poseidon and the UK


NOTE: the following article starts by mentioning the MOD's White Board. This is an element of the 10-years budget plan for defence, and it is important to read the following article not as a purely technical review or, worse, as a fantasy fleet exercise. This article is meant to be a realistic analys of the best way to close the Maritime Patrol Aircraft gap as part of the future investments in the 10-year budget. 
It is important, as a consequence, that you have an idea of what the White Board is, and how the MOD is planning for the future financial years. If you haven't read about it, or do not remember the details, check the budget explanation






One item i would expect to feature on the White Board at the MOD, possibly the most important piece appearing in the list, is a new, capable Maritime Patrol Aircraft. Even accepting the claim that Nimrod MRA4 was never going to be other than a budget-draining, flawed aircraft (and, to be sincere, I cannot believe it), the loss of maritime patrol capability is unjustifiable and very dangerous. The MOD was forced to admit that the Nimrod left holes all over the place, as it was a fundamental part of the military plans for eight out of the 15 security priority risks set out in the National Security Strategy and its loss “reduced our ability to conduct Strategic Intelligence gathering tasks, long range Anti-Submarine warfare [ASW], provide support to Search and Rescue, Maritime Security and power projection tasks.”

The NAO wrote a rather honest assessment of the Nimrod gap, but was actually too kind still.
 

The gap was felt during operations in the Mediterranean sea during Operation Ellamy, and US help was exploited, with the Americans providing airborne overwatch to the fleet. The lack of aircrafts to employ to track and guard the Russian navy carrier battlegroup “visiting” the UK’s shores was also rather embarrassing, and, while we won’t hear much about it, rumors have been circling about Russian submarines sneaking a bit too close to Faslane, now that there are no MPAs.

The MOD’s claim that the gap is being covered using other platforms and capabilities is just rubbish, and has been exposed as such by the NAO with the following observation:

Using other existing assets would provide a reduced capability compared with Nimrod, and diverting resources from existing tasks would have wider implications for defence. The Sentry surveillance aircraft is already at minimum crew and aircraft numbers to cover NATO commitments. Using helicopters, such as the Merlin or Lynx, would affect national commitments or training of crews for other tasks. Other alternatives are fully committed to current operations.

Not that it wasn’t evident already and we needed to hear that. The NAO statement is actually “generous” still, as the “reduced capability” actually does mean that while something can be done to drop a raft into the sea to aid Search and Rescue, and ships on the surface can more or less be tracked, there is no long range airborne capability to survey what’s going on beneath the surface of the sea.
8 Type 23 frigates (those fitted with the 2087 towed sonar) and the Merlin helicopters are all what’s left which is really up to the task of submarine-hunting and both platforms are already overcommitted as it is.

The security of the UK’s waters, shores, ports and nuclear deterrent submarines is at risk, and the ability of the Navy to set sail into dangerous waters where submarines could be in ambush has been dramatically reduced. It is very, very urgent and necessary to close these bleeding gaps, especially since even relying on allies in this area very much won’t do: NATO as a whole is short on Maritime Patrol Capability and is looking to pool what’s available to try and improve the overall situation. 

A series of studies are ongoing within the MOD on how to fill the gap, and there have been insistent rumors of deep interest for the P8A Poseidon, the new US maritime patrol aircraft. At one point in 2011, a purchase was given as imminent, with the UK expected to order 5 airplanes under the guidance of Royal Navy Commodore Simon Kings.
In the facts, it was premature, as there won’t be a chance to order a new MPA before the 2015 SDSR, but it is an indication of what the thinking inside the MOD is.   

An initiative to retain aircrew skills - dubbed Project "Seedcorn" – was started to place 33 UK personnel with maritime patrol aircraft squadrons in Australia, Canada, New Zealand and the USA in 2012, and represents an in-year financial commitment worth £3.2 million.

The Seedcorn effort will continue through 2019 under current plans, but both the committee and industry have questioned its sustainability: even ensuring that british crews have their share of action oversea with allies’ own MPAs, Seedcorn will only preserve a minimum core of knowledge, and not for long. If by 2019 the UK hasn’t filled the MPA gap, giving the crew an actual purpose, a career and airplanes to fly, quick, progressive loss of hard-gained experience will be unavoidable.

It has been reported that the british pilots posted to the UK (likely to be the majority) have been involved in bringing into service the P8A Poseidon in the US Navy.
Confirmations arrived from the US: the Chief Naval Operations (CNO) has designated the Commander, Patrol and Reconnaissance Group as lead for Maritime Patrol and Reconnaissance Force collaboration with U.K. on Maritime Patrol issues including support of P‐8 introduction. In detail, the UK and US have agreed on non-reciprocal exchange program for sending two experienced Nimrod crews to the US for a period of at least three years. In total we are talking of, approximately, 20 aircrew (4 pilots, 6 Naval Flight Officers NFOs, 5 Aviation Warfare system operators (AWs) and 5 Electronic Warfare operators EWs). The experienced personnel, welcomed by the US Navy, will contribute to the US Navy’s work in writing tactics and doctrine for ASW operations, and they are assigned, unsurprisingly, to the squadron VX-1, currently busy in bringing the P8A Poseidon into service.
It is possible that the early figure of 33 personnel changed, as the numbers do not add up: in addition to the 20 men assigned to VX-1, the UK government said in a Written Answer in November 2011 that agreements were already in place for sending 7 men to Canada to fly on the Aurora (local variant of the P3 Orion), 6 in New Zealand, of which 5 on P3 Orions, four men in Australia on the Orions and a further 3 men in the US, 2 of which on the Orions. SEEDCORN might have expanded to around 40 men, as a consequence.

The P8A Poseidon is on track to hit Initial Operating Capability (IOC) this year, and will then replace progressively the P3 Orion, with the Full Operating Capability (FOC) planned for 2019.
Six test aircrafts have been flying for years now, in the squadrons VX-1 “Pioneers” and VX-20 “Force” and the first (low rate) production aircraft has been delivered on March 4, 2012 to the squadron VP-30 "Pro's nest" in March 2012, based on NAS Jacksonville, followed by a further four by November 2012.
In the year that has just finished, the P8A also had the first deployment outside the US, when BuNo 167956, the sixth and last test aircraft, employed by VX-1, flew to the UK and operated out of RAF Lossiemouth for the Exercise Joint Warrior 12-1. It flew 6 missions for a total of over 36 hours. More hours were collected in a deployment in Australia and in trials over the Pacific Ocean.

In addition to six test aircrafts (T-1 to T-6), all flying, and to two static fatigue test airframes (S-1 and S-2, only the second being full scale) the US Navy has already signed three successive contracts for Low Rate Initial Production: a first 1.6 USD Billion order for 6 aircrafts in January 2011, another for 7 aircrafts in November 2011 and the last, in September last year, for 11 aircrafts at the cost of 1.9 billion.
And already in January 2009 the Poseidon won its first export order, with a 2.1 billion dollar contract for 8 P8 aircrafts in “I” configuration, named Neptune. India has options for more aircrafts, and it intends to exercise them in good time, bringing the total fleet up to 24 airplanes. The first P8I was delivered on December 20, 2012.
Australia has also joined in and plans to replace its P3s with P8s in good time. 

Now the US Navy is planning out how to continue the procurement of the P8 (a total of 117 Poseidon are to be procured, 108 of which are Production airframes) and it wants to move to a Multi-Year Procurement approach:

The Naval Air Systems Command (NAVAIR) intends to issue a sole source follow-on production contract to the Boeing Company for the production years FY15 through FY19 (Lots 3 through 7) P-8A Poseidon Aircraft. It is anticipated that this contract will be a five-year, fixed price type multiyear contract or multiple single year(s) if congressional multi-year contracting authority is not obtained. This procurement is for the manufacture of 72 aircraft (or other quantities as may be authorized and appropriated by Congress and/or for Foreign Military Sales) and related production support, to include special tooling and test equipment, systems engineering, production management, parts obsolescence, engineering change proposals and technical, administrative, and financial data. The Government plans to issue an Advance Acquisition Contract in FY14 for long-lead material and associated efforts supporting this procurement.

This indicates that two single annual orders are to be expected, one this year and one placed in 2014. The US Navy Reserve plans to procure 12 Poseidon to replace the P3C in its two Maritime Patrol squadrons.
The unit cost of the P8 in 2012 was $169.2 million. The airframe costs $111.43 million, the two CFM56-7B engines cost $20 million ($10 million each), and the avionics costs $31.57 million.

In 2011 the plan was to have one Fleet Replacement Squadron (with 12 aircraft) and twelve fleet squadrons (each with 7 airplanes), with the service life expected to be 25 years, but in November 2012 it emerged that basing and squadrons structure are still being decided.






As of 2012, the P8A Poseidon still suffers a number of issues and limitations, but most are expected to be removed and fixed already by the late-2013 IOC date. By 2015, when the UK could start seriously considering a purchase as part of the new SDSR, the P8A Poseidon should be a mature platform, which will be seeing its capability expanded with the first of several planned Increments.




Capabilities

The P-8 is, notoriously, a Boeing 737 passenger jet modified for Navy use: it has been given a weapon bay and it has been reinforced to cope with flying at extremely low altitudes over the sea.



The main sensor for the P8 Poseidon in the APY-10 radar, which is a vastly upgraded APS-137D(V)5 maritime surveillance radar and signals intelligence (SIGINT) system from Raytheon. The radar has been redesignated as AN/APY-10 in June 2006 due to the extent of the improvements and changes on earlier variants of the APS-137D system.

The radar is installed in the P-8’s enlarged nose fairing. It provides synthetic aperture radar (SAR) for imaging stationary ships and small vessels, coastal and overland surveillance, and high-resolution imaging synthetic aperture radar (ISAR) for imaging surfaced submarines and fast surface vessels operating in coastal waters. It has a color weather mode and a specialized Radar Periscope Detection and Discrimination (ARPDD) mode, for the detection of periscopes even at great distance.

The Indian variant, P8I, includes an additional Air-Air mode for the APY-10, which enables the tracking of airborne contacts as well. Another improvement present on P8Is is the presence of an aft-mounted, aft-looking APS-143C(V)3 Multi-Mode Radar (MMR) from Telephonics that, together with the APY-10, ensure 360 degree coverage. In addition, an interleaved weather and surface search capability has been added to provide the cockpit with up-to-date weather avoidance information while performing surveillance missions.



Northrop Grumman supplies the P-8's electronic warfare self-protection (EWSP) suite, which includes the Terma AN/ALQ-213(V) electronic warfare management system (EWMS), directed infrared countermeasures (DIRCM) set, radar warning system, and BAE Systems countermeasures dispenser. The Northrop Grumman ESM system for the P-8A has been officially designated the AN/ALQ-240(V)1.







L-3 Communications Wescam in Burlington, Ontario provides the MX-20HD digital electro-optical and infrared (EO/IR) multi-spectral sensor turret. The MX-20HD is gyro-stabilized and can have as many as seven sensors, including infrared, CCDTV, image intensifier, laser rangefinder, and laser illuminator.



The P-8I for India (“Neptune”) also an advanced integrated Magnetic Anomaly Detection (MAD) system from CAE Inc..

The US Navy plans to arm the P-8A with the MK 54 torpedo as main ASW weapon. A wide variety of anti-surface weapons, including SLAM-ER cruise missiles will also be employed. The weaponry, for a total of some 22.000 lbs (10 tons) is carried in an internal five-station weapons bay, on four wing pylons and on two centerline pylons, all supported by digital stores management allowing for carriage of joint missiles, torpedoes and mines.

Up to 120 sonobuoys are carried, and they are deployed by two reloadable rotary pneumatic launchers. The aircraft is fitted with the processing equipment and power to concurrently process data from 64 passive and 32 multi-static sonobuoys.



The P-8 has a nine-person crew: pilot and co-pilot in the cockpit, five mission crew at five mission consoles, a relief pilot and a in-flight technician. The consoles have dual 24 inch ultra-high definition screens, and there is space for growth, with room for a total of seven consoles, so that two can be fitted in future either for new uses and roles or just for workload sharing.



The P8 Poseidon has a 6 hours mission endurance at a range of 1100 km from the base, and 4 hours at a 2000 km range. Surprisingly, the P8 is built with a fuel receptacle that can be used to refuel in flight from boom-equipped tankers such as the USAF’s ones, but it does not have a probe to refuel from drogue-tankers, used by most NATO allies in addition to the US Navy itself (chartered, civilian-owned tankers from Omega services) and to the US Marines (KC130J tankers).



The P8A also employs a new hydrocarbon sensor to detect fuel vapors from diesel-electric submarines.


Awesome cutaway from Flight International





The Poseidon is the only maritime patrol platform in the world that promises comparable capabilities to those that would have been delivered by the Nimrod MRA4. The Nimrod would have been an absolute world leader, beating the P8 in every aspect, from the number of sonobuoys (150 against 120) to the number of weapon bay stations (9 vs 5) to, more importantly, sensors fit and, crucially, mission range and endurance.

Unfortunately, the Nimrod MRA4 is now gone, and the P8 is by far the best option among those available on the market. More importantly still, it has the potential to steadily grow more and more capable, expanding its reach in a number of roles as we’ll see. Crucially, while the Nimrod would have been a tiny fleet of 9 flying eccentricities, unseen elsewhere in the world, the P8 is supported by a huge fleet of civilian 737 and is also going to be in service in well over a hundred units with the US Navy alone, with perhaps as many as 24 in India, with more active in Australia and with more nations possibly to join in.

Keeping a british fleet of P8 airplanes flying and keeping their technology up to date would be immensely easier than going alone on the Nimrod path.




Adding capability



The P-8A was designed from the outset to incorporate additional “spiral development” of new weapons and equipment, and in the current plan the first such evolutional step is known as Increment 2. It should become operational around 2016, introducing important acoustic and communications upgrades. In addition, Increment 2 is also expected to introduce a new delivery method for ASW stores which is intended to eliminate the need for the MPA to fly low over the waters. 



Torpedoes still have to be released from low altitude, from 500 to 100 feet or less above the waves. Launches from higher altitudes would damage or destroy the current torpedoes, as they aren’t meant to survive the hard impacts with the sea’s surface that would be inevitable.

There are obviously downsides to this: for the maritime patrol airplane, flying low over the water is expensive in terms of fuel and stress on the airframe. In addition, flying low and steady to drop a torpedo makes the airplane vulnerable to enemy reaction: in recent time interest in submarine-launched anti-air missiles is on the rise, and in the near future such systems might well become a concern.

The most advanced offering in terms of Sub-Air missile is Germany’s IDAS, but there are other examples: France’s DCNS proposes a modern day mast-mounted Mistral missile launcher, which very much reminds of the much older (1972) british experimentation with the HMS Aeneas diesel-electric submarine. The Aeneas, already back then, was fitted with an extendable mast which included a cluster of 4 to 6 Shorts Blowpipe anti-aircraft missiles and the optics to aim them against enemy helos and aircrafts from periscope depth.



HMS Aeneas, the very special "SSG72", fitted by Vickers with the SLAM missile system. Demonstrating successfully in 1972 what DCNS is proposing today!




The selection of the 737-based P-8A Poseidon means that the US Navy needs to act on these problems, especially since the P-8A can perform low swoops if necessary, but its airframe is optimized for cruising at altitude. A wish to extend the useful life of the hard-worked P3 Orion aircrafts also contributes to the urgency for action.

The US Navy is, as a consequence, pursuing a way to launch torpedoes from high altitude, possibly also reducing the need for the aircraft to maneuver and turn to a suitable release point by having the torpedo itself navigating to the splash point. With the airplane no longer required to carry out complex maneuvers and turns at low altitude, the useful life of the airframe obviously is protected, and the airplane can serve for a longer time, undergoing less stress. Here comes into play the HAAWC (High-Altitude Anti-Submarine Warfare Weapons Concept), a program to take the US standard light torpedo, the MK54, and give it wings.  



Lockheed Martin puts forward the LongShot wing adapter kit: it enables the torpedo to glide on a range well in excess of 10 nautical miles and is also said to enable "off axis" launches so the aircraft doesn't have to maneuver to reach a precise splash point over a contact, but can immediately attack even if badly positioned.  

LongShot is described as a low-cost, self-contained wing kit, which is available for use on a variety of weapons, from bombs to cluster bomb dispensers and even sea mines. It includes a flight control computer, a GPS-based navigation system, and its own power source. Depending on the weapons it is attached to, and other factors, range can reach the 50 nautical miles.

Importantly, the LongShot does not require a MIL-STD-1760 interface, or even an electrical interface with the aircraft. This means that the system is particularly platform-agnostic and easily compatible and integrable on a wide range of aircraft, even older ones that would not normally be capable to drop GPS-guided bombs. This is important because it means LongShot does not require expensive, complex and time-consuming re-wiring of the aircraft and/or modifies to the interfaces of the onboard systems. LongShot can get the targeting information from a laptop computer or through an in-aircraft knee pad device that plugs into the aircraft intercom and establishes two-way communication with LongShot via the aircraft’s UHF radio. Integration of the system, in other words, promises to be extremely simple and quick.

Similarly, the LongShot wing kit is very simple to attach to the torpedo: the connection consists of two metal bands, that a device internal to LongShot forces open when the wing kit GPS confirms that the splash point has been reached. This means that the torpedo is maneuvered into the right altitude and position by the gliding wings, and is then released normally, as it was the airplane doing a traditional launch. The torpedo thus requires little to no change at all.

An HAAWC Mk54 torpedo was successfully demonstrated and launched at the Atlantic Undersea Test and Evaluation Center (AUTEC) in the Bahamas. The torpedo was launched from the weapon bay of a P3 Orion flying at 8000 feet of altitude, and it navigated its way to the release point, dropping the ordnance in the water as planned.


LongShot kit on MK54 torpedo




Raytheon also has its own proposal, the Fish Hawk, which is very similar in concept. The addition of a data-link to any of these two systems would allow constant upgrade of the splash point, ensuring the torpedo enters the water as close as possible to the target. Retargeting would also become possible. 

Fish Hawk kit from Raytheon



A Wingkit for sonobuoys could follow, and there has been talk of giving the P8A the capability to deploy a number of air launched UAVs: Boeing has been contracted to develop such a UAV, and came up with a Scan Eagle derivative the MagEagle Compressed Carriage, which in theory can be readied for several launch modes, including from capsules fired out of submarine VLS tubes. The MagEagle could also be armed with guided submunitions, and following launch from the aircraft could be recovered by a surface ship fitted with the ScanEagle recovery wire. A MAD-fitted variant (MAD Eagle Compressed Carriage, MECC) deployed from P8A Poseidons is meant to replace the capability of the missing aircraft-mounted MAD. The use of a drone allows the Poseidon to stay at altitude, as part of the “High Altitude ASW” concept of operations, which is expected to be implemented with Increment 2, going live in the fleet in early 2016. This suggests that both the MECC and the HAAWC should be validated and put in service by then.       

As a baseline, P8A will enter service with Level 2 interface with UAVs, which means the Poseidon is fully able to receive imagery and data directly from UAVs. With time, this will grow to Level 4 control, which means full control of the UAV and its payload, save for the take-off and landing phases.


Adding a Data Link to the wing kit of the torpedoes would make possible another big increase in capability, allowing corrections and retargeting up to the splash point



The P8A will make great use of sonobuoys to detect enemy submarines. A major improvement to sonobuoys is, as a consequence, planned: this is the Multi-Static Active Coherent, which is to be the main wide-area acoustic search system for the Poseidon. MAC works exploiting two different types of sonobuoy (source and receiver) and the onboard processing system. 

MAC is an upgrade to the Navy’s current Improved Extended Echo Ranging (IEER) system, which employs non-coherent sources to produce loud sounds that reflect off submarine targets; these echoes are then detected by receiver buoys.

MAC employs the same receiver buoys, but uses new coherent source buoys that enables multiple pings, optimized waveforms, and various ping durations, none of which the legacy IEER system provided.

MAC will begin operational testing on P3 Orions early this year, and integration activities for putting MAC on the P8 have begun in late 2012.



An even more relevant capability insertion is the Advanced Airborne Sensor (AAS), a powerful surface surveillance and target tracking radar. The AAS is a black program, classified: while some contracts and news have been disclosed, there is little publicly available data, and no visible budget nor technical reports. The new sensor, however, is said to be extremely capable, and there are proposals to use it, on P8 airframes, to produce a replacement for the E-8C Joint Stars of the USAF.

This new surface search and track radar is in itself the successor to another “black” radar system, the Raytheon APS-149 Littoral Surveillance Radar System (LSRS), which flies on a number of P3 Orion airplanes and only became known to the public in 2006, when Boeing was authorized to reveal the results of a simulation that saw a LSRS-fitted airplane (almost certainly an Orion) provide targeting data for a F/A-18, which was able to fire a SLAM-ER missile and hit a moving simulated missile launcher vehicle. The LSRS is a wide-aperture, Active, Electronically-Scanned Array (AESA) sensor designed for targetting-grade tracking of moving targets on land and at sea and to provide radar images of those targets to intelligence analysts. The P3 fitted with LSRS have been flying in support of land operations in the war against terrorism, reportedly due to its “groundbreaking” capability to track targets smaller than cars, all the way down to insurgents moving on foot. The LSRS is assessed to be “far superior” to the older APY-7 employed on the aging J-Stars of the USAF, and the AAS is an additional step forwards. An history of the LSRS is available here   


A P3 Orion seen with the LSRS "canoe" mounted under the fuselage. The AAS will be externally very similar, and will be installed in the same way on P8A.



On July 31, 2009 Raytheon was awarded a multi-year contract to begin development of the Advanced Airborne Sensor. In August, a second contract followed: worth $25 million, this was a contract modification awarded to Boeing to update avionics interface documentation for the P-8A Poseidon to clear the way for installation of the AAS.

In February 2012 Boeing received a $277 million contract the T-1 Poseidon test aircraft for aerodynamic and structural tests of the AAS radar pod. The intention of the US Navy is to purchase a number of AAS and “A kits”, which are the structural parts attached to the airplane’s fuselage to support the radar and fit them to a selected few P8s. It is suggested that 16 P3 Orion airplanes carry LSRS, so the number of P8 with AAS could be similar.



The capabilities of the P-8/AAS combination are such that Boeing is pushing for replacement of the existing, aging E-8 JSTARS fleet with a “P-8 AGS” fleet, which would be more effective, more easily sustainable and would cost possibly less than upgrading the E-8s with new engines, radars, and electronics.

AAS is useful on water as well as on land: it is meant to provide a targeting picture and guide missiles to their targets in a network, even in high-clutter, complex environment, for example in the littoral. Such a long-range, highly accurate radar guidance would make viable the proposed resurrection of the Tomahawk anti-ship, which could use in-flight updates from a P8 with AAS to strike enemy ships at extremely long range.

The AAS includes new features such as NetTrack, developed by the Defense Advanced Research Projects Agency, to track high-value targets—for example, key insurgent personnel and their vehicles—in high-clutter environments, by using high-range resolution radar measurements.



And the AAS is what would make the P8A a formidable joint asset for the UK, not just a submarine hunter.



Unmanned companion

The US Navy’s maritime patrol capability is going to improve massively in the coming years thanks to the large P8A fleet and, crucially, to its unmanned companion, the MQ-4C Triton, also known as Broad Area Maritime Surveillance (BAMS), which should hit IOC in 2015. The MQ-4C Triton is a special variant of the Global Hawk High Altitude Long Endurance unmanned aerial vehicle.

The Tritons will be assigned to two Squadrons (West and East), distributed each on a Main Operating Base and on a number of Forward Operating Bases, with the MOB being the main maintenance center and having the Mission Control System.



The West Coast Squadron has its MOB at NAS Whidbey, with the drones deployed on the two Forward Operating Bases Beale AFB and Andersen AFB (Guam island).

The East Squadron has its MOB at Jacksonville, a FOB on the East Coast yet to be determined, another at NAS Sigonella in Sicily and another with the US 5th Fleet (C5F), under CENTCOM, in the Indian Ocean.


MQ-4C Triton



The Triton at entry in service will be capable of Surface and Air-to-ground 2D AESA radar surveillance on 360° and will also have a 360° field of view for its EO/IR turret, plus a capable AN/ZLQ-1 ESM fit. A Signal Intelligence capability is planned for insertion in 2019, and in 2021 the BAMS will also be given Robust Communications Relay and Networking capability to expand the communication lines available to surface ships and ground forces.

To help in the ASW mission, BAMS is to fitted with the same hydrocarbon sensor installed on the P8A.



The most impressive feature, however, is that the US Navy plans to build up a 65-strong fleet capable to sustain, 24 hours on 24, 7 days on 7, all year long, a constant surveillance orbit with a minimum range of 2000 nautical miles, from each of the 5 BAMS bases.


The impressive BAMS coverage. Curious to see that the "Atlantic Gap", which so much of a worry was during the Battle of the Atlantic, is still there, even with modern technology.



At Full Operating Capability, in 2020, it is planned that a force of 866 men will support the BAMS arm. Training for the use of BAMS is expected to be 100% delivered by simulation: BAMS aircraft will generally not be used to meet or maintain training and readiness except in early development before simulators are

delivered. The total cost per unit is $186.463 million, so it’s great capability, with a cost.



The UK can of course not afford such an investment, but the Royal Navy is said to be involved with the compilation of the list of requirements for the future SCAVENGER Medium Altitude Long Endurance unmanned air vehicle the RAF is pursuing: aircraft carrier compatibility is not going to be available, but we can at least hope that the machine coming out of SCAVENGER will have some decent capability in surveillance over the sea.



Towards a P-8K?


We should not forget that the Nimrod MRA4 itself was going to be a supremely useful joint asset, with great capability on land as well as over the waters. Its radar and sensor turret and extremely long endurance made it useful, as the MR2 proved abundantly serving over Afghanistan.

MPA aircrafts do work in support of land operations very frequently: Australian P3 Orions, among others, have been working over Afghanistan for a decade, and in these days the French are using Atlantique planes over Mali.

The Nimrod MRA4 would also added, however, more extensive and specialized capabilities, including a formidable battery of radios and communications equipment and sophisticate ELINT gear, namely the Israeli Elta EL/L-8300UK Electronic Support Measures (ESM) suite, a powerful ELINT system, which would have enabled the Nimrod MRA4 to detect all sort of electronic radiations and turn them into valuable intelligence data. One operator was assigned to the ESM, and the MRA4 would always carry a “swing-role” operator on another console which could help for communications.


The Nimrod MRA4 would have been a true world beater



A british P-8 would have to be a joint asset, useful in a wide range of scenarios. So true this is, that the work being done to assess the MPA requirement is done under budget control of the Joint Forces Command. In the words of government, the future procurement of a Maritime Patrol Aircraft will necessarily pass through a wider study known as Air ISTAR Optimisation Strategy (AIOS): 



[...] the Department currently has no defined requirement for an MPA capability. The study into Wide Area Maritime Underwater Search (WAMUS) concluded that in the near term the most appropriate solution to a potential underwater surveillance requirement was a manned aircraft, but the Department’s longer term objective is to merge as many surveillance requirements as possible into single equipment builds (e.g. radars that can operate in multiple modes and in all environments) and to further refine platform types, capabilities and numbers to achieve maximum effect at minimum cost. As such, those requirements previously covered by the Nimrod MR2/MRA4 capability are now integrated in the Air ISTAR portfolio and work is underway in the form of the AIOS to understand how these requirements can be best covered from the current and planned Air ISTAR Fleet.



The initial findings of the study will be reported to the Military Capability Board (MCB) in April 2013. Those options that appear to merit further investigation will then be developed to inform a MCB Genesis Option Decision Point prior to CSR15/SDSR15. As set out above, we will keep the Committee informed of our work in this area. In the meantime, we have investigated what military off-the-shelf capabilities exist. For comparison, generation of the AIRSEEKER airborne signals intelligence capability, replacing Nimrod R1 through an extension to the US RIVET JOINT aircraft production line, will have taken just under five years from the identification of the requirement to reaching Initial Operating Capability. Should the situation warrant it, adoption of off-the-shelf platforms, coupled with the Seedcorn personnel, could establish a capability in significantly less time.



What are the challenges, and the gains, of a possible british purchase of P8 (possible designation P-8K)?

The challenges relate, mainly, to costs. For example, due to its much shorter range and endurance when compared to Nimrod, the Poseidon would very much need to be fitted with an air refueling probe. It shouldn’t be technically nor economically unfeasible, but of course it is an additional expense that the MOD might well try to avoid, even if it means losing a good bit of capability.



Another “challenge” would be to put the LongShot or Fish Hawk wing kit on the Stingray torpedo. Again, this should be relatively cheap and straightforward, but in the current climate, nothing is cheap enough. Not adopting the US “High Altitude ASW” modus operandi would not be a wise decision for many reasons, including the much faster aging of the airframe.

At the same time, going High Altitude could well mean having no MAD if the UK does not follow the US lead on the UAV-mounted MAD.



The UK would also have to fund the integration of Stingray, and, hopefully, of other weaponry. In a “Joint” vision, the P8, like the Nimrod MRA4, should not be seen as “just” an ASW platform, but as a long range hunter-killer, capable to operate on water as on land, detecting, tracking and hitting targets of the most various nature.

With time it would be very much beneficial to integrate weapons such as Storm Shadow, SPEAR 3 and Paveway IV. The rebuilding of a long-range anti-ship capability would also very much be welcome, as the loss of Nimrod has also meant the loss of the air-launched Harpoon. With Sea Eagle having gone even earlier, the UK is currently very low on anti-ship capability.



The UK should also make sure to acquire the AAS radar and related A-kit, even if it means investing more money. This investment would give the joint forces a truly world-beating capability, useful in any scenario. In exchange, and to partially absorb the costs of the P8, the UK should withdraw from service the Sentinel R1 fleet, using the Poseidon as a replacement for it, as well as for Nimrod. This not because the Sentinel is an underperforming system or anything I’m eager to lose (who follows me knows well how I totally opposed the dumb SDSR idea of withdrawing it without replacement) but because the Sentinel can’t be of much help beyond its current intended role, despite what politicians try to sell to the public. Possibly a radar mode for surface tracking of ships could indeed be added, but there’s too few airplanes to start with, they have no ASW capability at all and they really haven’t got much margin for any kind of growth, when you consider that even the original requirement for fitting a refueling probe was dropped for weight problems.

A fleet of Poseidon aircrafts (which, also considering the inferior range compared to Nimrod, really should number no less than 9, and ideally more) can instead cover a multitude of roles, and do well in all of them:



-          With AAS, it is an excellent replacement for the SAR-GMTI Sentinel R1;

-          It reintroduces much needed maritime patrol capability, including the crucial ASW capability, which is the very reason why we bother with MPAs anyway; 

-          It provides ISTAR and precision, long range strike



As we said earlier, there is also room for growth, which could well include fitting of the Elta EL/L-8300UK Electronic Support Measures (ESM) suite planned for the MRA4. I can’t think, honestly, of a more flexible and useful joint asset. 




P8A Poseidon with AAS


Finally, and importantly, there is justified hope that the P8 Poseidon could offer some sizeable interoperability advantages, and be "cheap" by building on the logistics of the 117-strong US fleet. Upgrades and maintenance of the new plane could be done cheaply and timely by inserting the UK planes in the scheduled maintenance plan for the US ones, exactly as will be done with the 3 UK Rivet Joint to be put in service in 2014 as Nimrod R1 replacement under the "Airseeker" programme. These 3 UK planes will top the 17 US ones, creating a single, joint fleet of 20 planes to be maintained cooperatively under a Memorandum of Understanding: every 4 years, the planes will return to prime contractor L3 Communications in Greenville, TX for a complete strip down, refurbishment, and system upgrade. What’s even more ground-breaking is Britain’s joint participation in platform improvement, under a continuous capability improvement program that is contracted until 2025, with options to extend work beyond this period: Britain will be at the table to write the requirements and inform the evolution of the type.

This is the approach that could and should be followed for the P8 Poseidon, as it has potential to deliver massive savings, and machines always up to top specs.



Based in Waddington, a fleet of P8s would fill a huge gap in capability that the SDSR 2010 has created, and it would make the future plans for expeditionary forces much more coherent and believable. As always, costs are difficult to estimate, but the flyaway unit cost of a P-8A for the year 2012 was $169.2 million. The cost rises to $197.8 million including support costs.

The airframe costs $111.43 million, the two CFM56-7B engines cost $20 million ($10 million each), and the avionics costs $31.57 million. This is likely not the price the UK would pay if it ordered the airplane (it would be higher, as there would be start-up costs the US Navy has already faced, and there would be national requirements such as Stingray integration, too), but it is a basis for an estimate, and is, at least, a relatively comforting figure. The total cost per unit of the P8A for the US, including development costs, is 270.240 million dollars, as of 2011. 

Considering also the favorable exchange between pound and USD, it isn’t a bad deal.



Friday, January 11, 2013

Gaps, gaps, gaps - part 2



Part 1 of this report: Gaps, Gaps, Gaps


Next in line is the FRES SV vehicle family. Unfortunately, the NAO report covers a period that ends before the most interesting developments. Following confirmation of the enduring requirement for FRES SV at the completition of the SDSR, and indeed following the army restructuring program (Army 2020), the number of vehicles to be purchased and timings have all changed.
Entry into service will happen at least 9 months later than originally planned. The date is not disclosed, but we are possibly looking at 2018, if not later. I've read that CVR(T) vehicles will not be entirely gone before 2026.

An option that could be given the go ahead in the immediate future would however partly compensate the delay to entry in service by bringing forwards development and demonstration of the RECCE Block 2 group of vehicle variants.
The FRES SV has been broken down into multiple parts, all with their own decision Gates. So far, activity has focused on RECCE Block 1 (Scout vehicle, Armoured Personnel Carrier, Repair, Recovery and Common Base Platform) but the Block 2 could now be added to the ongoing activity, to demonstrate Ambulance, Command Post and Engineer Recce variants.
Part of the Block 2 should also be the Joint Fires direction vehicle, destined to carry a full six-man Fire Support Team of the Royal Artillery, with full equipment for the direction, under-armor or dismounted, of mortar, artillery and air attacks.

A RECCE Block 3 is also envisaged for the future, but budget uncertainty makes me be particularly careful about these future, as yet uncommitted to parts of the program. Bringing forwards demonstration of Block 2, to include the vehicle variants it covers into the Initial Operating Capability would be a very welcome move, as it would greatly increase the chances for the Army to actually get the vehicles it needs.

The Type 45 destroyers are now going strong, and the program has achieved a very positive in year net cost variation of -108 millions, which have been handed back for use elsewhere in the equipment programme. Reportedly, this year we'll see up to four Type 45 fitted with Harpoon missiles, presumably coming from the retired Type 22 frigates, but the NAO does not speak about it. Major improvements in Combat System software and communications (SATURN has been fitted) are reported.

The Typhoon Future Capability Program is, as always, a source of misery. While the Typhoon program registers a positive result, with a cost reduction of 69 millions, the Future Capability Program 1 for introduction of advanced Air-Ground features reports a 22 million cost increase (to 441 million) and, more importantly, a massive 18 months delay, to December 2013, which also affect the Meteor as we have seen before.

A combination of technical complexity, Partner Nation disagreement on a synthetic training solution and delays in agreement of an international support arrangement have caused the delay.

Anyway, the SDSR has pushed to the right the requirement for Typhoon ground-attack capability to 2015.
Future Capability Program 1 introduces Paveway IV, full functionality of the Litening III targeting pods and other improvements.
Future Capability Program 2 will follow, at some point, hopefully including integration of Storm Shadow and Brimstone.

An Active Electronic Scanned Array voice has made its appearance into the Report, with Initial Investment Decision made in July 2011, but no other detail is provided. The budgeted-for date of entry in service is currently classified.

Regarding the Warrior Capability Sustainment Programme, the NAO reports that the current plan is for the upgrade of 445 vehicles (all variants, including FV514 Artillery Observation Post, but excluding the Battery Command vehicles which appear not to be in use anymore, with a number having been converted in Ambulances by the REME for use in Afghanistan) from an affordable fleet of 565.
The FV514 vehicle is very important to the future of the Royal Artillery. As part of WCSP it is getting mechanical, electric and protection upgrades, but a separate programs will have to be funded at some point to upgrade the fire targeting and direction equipment. I plan to write an article in the near future looking in more detail into the Warrior situation, and more info will be provided there. 

Importantly, the NAO report confirms that the Armored Battlefield Support Vehicle element is not dead, despite having been silent ever since it was made a part of Warrior CSP by the 2005 defence industrial strategy.
The ABSV is described as:

A new variant, replacing obsolescent platforms, that has equal protection and mobility to the core fighting platforms. Armoured Battlefield Support Vehicle is currently in the Concept Phase and is subject to future approval.

The ABSV, also known as "turretless Warrior" is meant to replace a number of FV430 tracked vehicles inside armored infantry battlegroups. Also known earlier as Battle Group Support Vehicle (BGSV) and earlier still as M1P1 (tracked vehicle which was accompanied by the also cancelled M2P2, the 8x8 Boxer vehicle), it has had a complex history to say the least.
At least 3 prototypes were ordered to then Alvis Vickers, and at least one was built and demonstrated. The requirement has varied anywhere between 125 and 300-plus vehicles, with Ambulance, Command Post and General Support variants envisaged.

With how things are evolved over the years, now ABSV and FRES SV Recce Block 2 are kind of in conflict for the same roles, replacing FV430 vehicle variants.
Using turretless Warriors for the roles might cost less than build a wholly new FRES SV, and of course having almost all the battalion using Warrior mechanics is good for logistics, but insertion of technology which is so important for Command and Ambulance vehicles in particular suggest that going for a new, modern FRES variant is desirable.

However, the FRES Engineer/Bridgelayer vehicle has been cancelled, while a Warrior bridgelayer prototype has been showcased in 2011. Since the requirement is still there (some 35 vehicles were envisaged), to support the FRES Scout, ABSV might end up delivering Bridgelayers instead of ambulances, command posts and APCs.
There is also another requirement that has been ignored this far, which is that for a Mortar Carrier replacing the relevant FV430 variant currently in use. As the Mortar Carrier role should not require a too complex modification to the Warrior hull, and since the requirement would be for a low number of vehicles (between 6 and 9 vehicles for each armoured infantry battalion, so around 54 at most) it might make sense to convert surplus Warrior hulls as a low-cost, big-gain program.

This way, FRES SV RECCE Block 2 would replace APCs (not overly complex, but required in significant numbers that Warrior wouldn't be able to cover) and the complex Command, Ambulance, Communications and Engineer Recce / Joint Fires variants, while surplus Warrior hulls could be used for covering the need for Bridgelayers and Mortar Carriers. The numbers are also compatible with what the NAO says, as 565 - 445 gives 120, a number of hulls more than adequate to meet the two requirements i suggest to tackle.

IOC for Warrior CSP remains defined as one Armoured Company equipped and trained collectively at Level 2. Expected in November 2018.

Among the pre-Main Gate programmes appears MARS, which will of course move up into Post-Main Gate in the 2013 report, since the contract has since been awarded for MARS FT.
The NAO report confirms what i had already reported: the procurement of the MARS Fleet Solid Support Ships currently sits on the White Board, waiting to be given the go ahead later in the decade, post SDSR 2015.
Money is planned to be provided from the core budget for assessment phase of Solid Support in the coming budget cycles.

One major, welcome programs in Pre-Main Gate phase is the Network Enabled Airspace Defence and Surveillance (NEADS), which is the Army's effort to modernize the obsolete air defence capability currently available.
A very complex program, it is considered of prioritary importance by the Army since future operations are expected to be conducted in far less permissive environments. NEADS is meant to expand the defence capability to give protection from the whole range of threats: aircrafts, helicopters, cruise missiles and, very importantly, against UAVs and Rocket-Artillery-Mortars. 

Three Increments are planned:

Increment 1 will replace Urgent Operational Requirement equipment with an enduring Counter Rocket Artillery & Mortar automated sense and warn capability from 2015.
This capability is being used in Afghanistan to protect UK bases from rocket artillery and mortar attack. This was provided under Treasury Urgent Operation Requirement Funding. Automatic Sense and Warn capabilities will be brought into the core equipment programme.

Increment 2 will deliver an initial Counter-Unmanned Air Vehicle Capability and replace the existing Counter Rocket Artillery and Mortar intercept capability from 2017 as well as sustain ground-based air defence in the Falkland Islands beyond 2020.


Increment 3 will improve protection against the remainder of the Difficult Air Targets with Full Operating Capability expected in 2027.

The Difficult Air Targets set includes cruise missiles, Unmanned Air Vehicles, Attack Helicopters and Rockets, Artillery and Mortars.
 

Automatic Sense and Warn UOR is an adaptation of the Land Environment Air Picture Provision (LEAPP) equipment program for Afghanistan needs. Another element is JAPPLE. In 2011 i wrote this description, which should still be at least partially valid, even though not much info is available on this kind of systems, for obvious reasons.

The Joint Air Picture Provision of the Land Environment is active in Helmand since 2008. A team of eight, split between Camp Bastion and Lashkar Gah, provide the Joint Helicopter Command and to the Combined Forces HQ a 24-hours complete picture of activity going on in the air, to direct air defence efforts and de-conflict the Joint Helicopter Command routes and missions with the concurrent artillery fire or othe potential threats. In addition to this constant presence, the system also deploys small forward teams with troops where necessary. 

JAPPLE builds on the capability provided by the Automated Sense and Warn system: this was procured as UOR for Afghanistan, and is a combination of software and hardware capable to fuse together information coming from a number of sources, including MAMBA artillery locating/battlefield surveillance radars. Mainly, though, it uses two Giraffe ABM radars. The information is fused and transmitted on the LEAPP C2 network, and alarm of incoming attack is launched via the Waves towers installed in based in Afghanistan. Two Giraffe radars are in Bastion, two in Kandhar.
In the system, at some point, is likely to be integrated also the flow of informations coming from B-ISTAR sensors.
The whole system is currently manned by 5th Regiment RA, with the support of roughly one battery deployed on each Herrick cycle by 16 RA.

LEAPP in itself (Land Environment Air Picture Provision) is a little known but invaluable programme which is going on from a few years, and that allowed the advanced JAPPLE to happen. LEAPP provides near real time correlated air picture for the land environment. It is a combination of control nodes and organic sensors, and a vital software, Bowman data radio-compatible, capable to link and connect all Royal Artillery assets (artillery batteries receive info and feed back into the system the data of their own firing trajectories, so that all things moving in the air can be mapped). LEAPP is deployed at formations Hqs, and provides its air picture to all users via NATO data link 16 and 11.





The report says that the C-RAM interception capability will be replaced in 2017, but please note that the British Army currently has not an in-service C-RAM interception capability. ASW is a detection and warning system only.
In Iraq, the Army deployed, as UOR, a number of american-made Centurion C-RAM trailers, fitted with suitably modified Phalanx CIWS guns taken from the Royal Navy's stock. However, for what i understand that was a temporary solution: Centurion was not deployed to Afghanistan, the trailers have been handed back to the US and the Phalanx guns returned to the Royal Navy.
The "existing" C-RAM capability is virtual, but a C-RAM protection system was promised in SDSR documents. Nice to see that they are sticking to that promise. 

We can assume that  connected to NEADS will also be the replacement for the now retired COBRA counter-artillery radar and for the active MAMBA: the Common Weapon Locating Radar, which should be the ARTHUR Mod C from Saab.
Entry in service should be in 2014 but an order has not yet been finalized.

Some 34 US-made Lightweight Counter Mortar Radar are in use after being procured as UOR. Most of them are in Afghanistan, but a number was also used to provide protection to the Olympic games in London. It's near certain that these precious radars are part of the solutions being brought into Core Budget.

The NAO does not go into such detail in its report, but includes this information:

Approval for the Assessment Phase 1 was given by the MOD Investment Approvals Board in February 2010, and ratified in June 2010 as part of the review by the new coalition Government.
The objective of the Assessment Phase 1 is to establish the most cost effective solution to the Increment 1 requirement and early de-risking activities for Increment 2.
The current approval covers Assessment Phase work required to reach Main Gate 1, which leads to the Demonstration and Manufacture phase for Increment 1 and effectively Increment 2 Initial Gate. The Assessment Phase has been structured into three workstreams as follows:

a. Workstream 0. Initial de-risking activities will identify and address any changes and further lessons learnt as a result of the evolving Land Environment Air Picture Provision and Urgent Operational Requirement projects and current operations. Further work will develop the architecture required to allow the incremental insertion of capability over the project lifecycle. This will also drive coherence into future Urgent Operational Requirement activity and address any scaling issues as a result of the Defence Review.

b. Workstream 1. The work stream will result in the down selection to a single affordable option to be presented at Network Enabled Airspace Defence and Surveillance Main Gate 1 to deliver the Automated Sense and Warn capability. A full option analysis will be undertaken to investigate retaining extant Urgent Operational Requirement and Core Programme components as well as alternative off the shelf solutions.

c. Workstream 2. This work stream will result in the development of a detailed system architecture and associated systems and technical requirements and initial evaluation of potential equipment options. It is planned to de-risk the overall Network Enabled Airspace Defence and Surveillance architecture, by integrating Future Local Area Air Defence Systems (Land) and High Velocity Missile models/ equipments into a representative Network Enabled Airspace Defence and Surveillance system and also undertake an initial assessment of Counter-Rocket Artillery and Mortars effectors.

In 2010, associated with the Strategic Defence and Security Review a number of options were raised to maintain alignment with wider Defence priorities. These were primarily associated with scaling and delivery timings.

An Industry Day was held in November 2010, at which a number of companies were briefed on the programme. Since then industry have been kept informed of developments via a series of newsletters. A series of one to one discussions with industry on Increment 1 is currently being conducted, following the Request for Information for Increment 1.

The NAO notes that, as of March 2012, NEADS activities were on track and making good progress towards the first Main Gate point. The Main Gate expected date, however, is classified and obscured in the report.
Surprisingly, the NAO shows FLAADS(L) as expected to hit IOC or even In-Service date in November 2016: i'm not sure how we should read this passage, however. While FLAADS(M) has long been expected to start replacing Sea Wolf on the Type 23s from 2016, Rapier replacement was expected not to be funded before 2018 at the earliest. I'd be surprised if it had been brought forwards.
Not because it is not needed, but because of budget considerations.

Another program of interest is the already mentioned upgrade to the Spearfish torpedo.

Spearfish is the sole heavyweight torpedo in the UK arsenal and is carried aboard Trafalgar and Vanguard Class submarines. The weapon was introduced into service in 1994 and is the only submarine launched weapon for offensive and defensive operations against ships and other submarines. Spearfish will be deployed in the Astute Class from 2013 and an upgraded Spearfish weapon is the planning assumption for equipping the future Deterrent.

The Spearfish Upgrade project is required to deliver a mid-life upgrade to sustain a credible and safe weapon for future submarine operations. The scope of the project includes digitisation of the weapon, the provision of a new insensitive munition warhead to replace the current ageing warhead, changes to the fuel system and the introduction of a new communications link. The upgrade will address obsolescence and also enable future reductions in through life costs.

Assessment Phase began with a contract assigned to BAE in April 2010, and will be completed in April 2014 with in-water trials. So far, the effort is progressing satisfactorily and on time. The new Insensitive Munition compliant warhead achieved the required level of technological maturity in January 2012 completing successful land based and underwater scale test firings undertaken in Germany and in the UK respectively.

The fibre optic dispensing system evaluation trials in April 2011 proved that the fibre in use was too weak and required replacement with a more ruggerized one. There are no delays to report anyway.

Initial design work to define and develop the interface between the upgraded weapon and the submarine combat system was completed in February 2012. Work is ongoing.

Regarding CEC, the NAO unfortunately confirms that:

Planning Round 2012 has announced United Kingdom Cooperative Engagement Capability Project Delete Option E12AW006S has been taken and is not part of the funded Core Programme. Delete Option also identified £1m to conduct project close down activities in Financial Year12/13.

It is a big loss of capability, in particular for the Type 45 destroyers. It is not clear how this PR12 decision affects the possibility, for the Navy, to resurrect the CEC effort in the coming years.

Particularly unwelcome is this passage:

Once the Sea King leaves service there will be some consequent capability gaps until upgraded Merlin helicopters can take on the tasks of providing helicopter lift from naval vessels to the shore (a two-year gap until April 2018) and providing airborne surveillance and control capabilities for the future aircraft carriers (a potential four‑year gap until 2020). The Department is examining alternative means of closing these capability gaps.

Regarding Crowsnest, the intended replacement for the Sea King MK7 ASaC, we will know more this year, if plans do not change: assessment phase will finally be launched. Avoiding this particular gap is extremely important.
Just as unwelcome is the gap in amphibious support helicopter capability. It is not clear how this must be read: the plan so far has been that in 2016 the Commando Helicopter Force will take over the Merlin HC3/3A, but properly "navalized" HC4-standard airframes were not going to arrived before 2017.
In the disaster, we have to hope that the April 2018 is the new date for conversion to HC4 standard of the Merlins: if the delay is to be intended as total lack of helicopters for CHF for two years due to postponed Merlin transfer, the only sane option is keeping the Sea King going for a little longer. It would be totally irresponsible to do otherwise.



Finally, they have nothing to do with the NAO report, but they are relevant news:

- The british armed forces have selected their new sidearm: it's the 9mm Glock 17 Gen 4 pistol, fitted with Picatinny rail under the barrel. It is lighter than the Browning, the clip holds 17 rounds (vs 13) and it allows much shorter reaction times from draw to firing of a full sequence of 5 rounds.

25.000 pistols have been ordered, at a cost of 9 million. Afghanistan-deployed troops, of course, will get the weapon first. Firearms distributor Viking Arms Limited, of Harrogate, will deliver guns and holsters.

- An UOR has also been financed to procure a number of LSD500 laser surveillance and sniper detection systems from France's CILAS. The systems are for use in base protection in Afghanistan.
I don't question the wisdom of the purchase which i'm sure is made for good reasons, but bases have already the Boomerang III system, while soldiers have seen the UOR for a body-worn or rifle-mounted sniper detection system cancelled last year. I would have preferred to fill the capability gap in terms of wearable/rifle mounted shooter detection system first, to extend the capability to foot patrols away from FOBs and vehicles (a number of vehicles in theatre are fitted with Boomerang III). 


Thursday, January 10, 2013

Gaps, gaps, gaps - part 1



Part 2 of this report: Gaps, gaps, gaps 


The financial management of complex military programs is improving, but military capability is being eroded at alarming rate. This is what the NAO Major Project report 2012 exposes. The thick of the cost escalation is due to inflation factors that sit outside the MOD’s possibilities of control. In fact, after five years in which this expenditure voice wasn’t updated, expected fuel costs for the Voyager air tanker’s service life have been revised, and they account for an expected cost growth of 336 million pounds. Fuel cost is not something the MOD can do much to control and dominate, as the NAO itself notes.

In total, there has a net total increase of 637 million pounds over a number of programs, most notably FSTA (Voyager) and the CVF aircraft carriers. Other programs are now under control and costs connected to them are falling, so that the increase in expected expenditure compared to last year is ultimately  worth 468 million.

The Voyager tankers are also incurring a 31 million pounds cost increase due to inflation, 2 million for the implementation of additional safety measures and 24 million due to France stepping out of the frame: it had been hoped that the French air force would buy Voyager services to remedy to the shortage in air to air refueling capability, but an agreement wasn’t found and ultimately France is planning to order this year the first few of its own planned 14 A330 MRTT.  
The FSTA program for Voyager tankers has also achieved savings in other areas, however, with a noticeable reduction of 98 million due to the refinancing of the PFI deal.
The final balance of savings and cost increases, however, puts the Voyager on top of the list of the naughty boys, with a net increase of 257 million.

CVF follows, reporting a 217 million cost increase, in no small part due to the switch from STOVL to CATOBAR. The NAO report covers the CVF situation prior to the switch back to STOVL and F35B, which will be covered in the 2013 NAO report. Until then, it will be difficult to say what the real impact on the program was in terms of potential delays and additional costs. Later this year the NAO will release a new report into the delivery of Carrier Strike, so we might obtain the up to date, valid information from it. There’s many questions still waiting to be answered regarding the CATOBAR saga.

The A400 Atlas C.1 cargo plane program reports a 163 million net increase in costs, mostly due to the Export Levy payment made by the UK as part of the multinational agreement to keep the program alive. The UK share of costs is 175 million.
In theory, EADS will hand the money back if export orders are won in the future, but we’ll see how it actually goes. The MOD has prudently decided to consider this money as a cost increase. If it'll return at some point in the future, all the better.

Importantly, the NAO also observes:


In recent years we have reported several times that the Department has had to slip projects or cut equipment numbers to bridge the gap between estimated funding and the forecast cost of the defence budget. These decisions were not value for money and meant that new capabilities were not available on time. There are no such instances recorded this year, though difficult decisions may still be necessary as part of the Department’s drive to keep the Equipment Plan in balance.

If financial management is showing improvements and discipline is starting to have a beneficial effect on accounts, the situation for military capability is however dire in several areas. Particularly worrisome are Air-Air-Refuelling, airlift, embarked AEW and Amphibious support helicopters.

At various points to 2017, there will be critical gaps in air transport and air-to-air refuelling capability. From 2022, there will be approximately a one-third shortfall in tactical transport aircraft against the stated requirement. On the ability to move passengers and cargo by helicopter, the Department has accepted that while there will be a shortfall against the full requirement, it believes that current plans will deliver a sufficient capability, and the risk will be reduced by using other defence capabilities.

Main contributors to the reduction of planned expenditure are Typhoon, Type 45 and Astute (boats 1 to 3) which have been able to hand back the major part of the 169 million pounds recapped in 2011/12 over the programs examined in the report.
This money was contingency funding that proved not necessary and could be put back in the central money pot.

The entry in service of several capabilities, however, has slipped to the right by a combined 139 months. An enormity, with the Brimstone 2 and Meteor missile programs being the biggest contributors, with twin 23 months delays to report.
CVF reports a 9 months slippage, but as we said, the "photograph" of the NAO has been in this case been made outdated by the switchback to STOVL: construction of the ships as of now seems to be going strong, several milestones have been hit earlier than planned on the assembly of Queen Elizabeth and i'm consequently willing to guess that the NAO report 2013 and/or Carrier Strike report will rectify this particular data. 

Anyway, delays and gaps. This is where the pain comes. Let's look at the military capability, and see what the situation is.

A400 Atlas C.1

Entry in service still expected in March 2015, no further delays on the horizon.

The plan is to hit IOC in 2015 with 70 Squadron RAF fielding the first 3 Atlas cargo planes.
Full Operating Capability will be hit over 2017/18 with 12 airplanes operational.

The first UK airplane, MSN16, is expected to be delivered in 2014. It will the 16th production A400 aircraft, but the UK took the conscious decision in previous planning rounds to be patient and wait a little, in order to receive all aircrafts at production standard and with software SOC 1.5: this standard means the aircraft is fully ready and cleared for all kind of airdrop operations and is ready for the Air Tanker role, although the RAF so far does not plan to procure AAR kit for the Atlas.

The early planes, delivered to France and others, come at standard SOC 1, which is very much an early release, with some limitations.

SOC 3, expected in 2018, will add the full capability for low-level tactical flying and Special Forces role.

It is also confirmed, as announced for the first time in 2008, that the madness of not having fuel-inerting system on the RAF A400 has been terminated: the MOD has paid some 6 millions to have fuel inerting pipes installed and has invested to add a Portable Removable On-Board Inert Gas Generation System. This greatly improves safety.

The installation of full Defensive Aids Sub-System (DASS) has also been brought forwards, and the full range of countermeasures, including Directed Infra Red Counter Measures (DIRCM) will already be on the first airplane delivered.
As of now, however, it would appear that DASS is funded for the first 9 airplanes only. Obviously, this is unacceptable, and it will have to be corrected as soon as possible in the next planning rounds. 

22 airplanes remain planned for entry in service by 2022, when the C130J is expected to retire. The NAO however reports that the Atlas alone are insufficient, with a one-third shortage in tactical airlift capability anticipated. Not a case that, prior to SDSR 2010, the C130J's OSD was 2030, and not 2022.

In the immediate future, the situation is just as complex, with measures urgently needed to improve availability of C130Js and a further delay having been imposed to the retirement of the last 8 C130K to October this year, at a cost of 16 million. The end of the old C130Ks has had to be delayed several times in a row now, and this of course has a cost.

The Urgent procurement of 2 BAE 146 Quick Change tactical cargo aircrafts cost 47 million pounds.



AIRSEEKER

The procurement of 3 Rivet Joint airplanes for COMINT and SIGINT tasks is on track, but reports a 4 million cost growth due to exchange rates variation.
At full operating capability, the Rivet Joint force will consist of 3 airplanes, 4 trained crews, 2 deployable ground stations for data processing, ground infrastructure for support (at the Main Base, RAF Waddington) and a ground intelligence analysis and exploitation facility (to be built at the Joint Services Signals Unit, RAF Digby base).


C17 number 8

Cost for the 8th C17 was 215 million.

There's no mention in the NAO report, but rumors are circling about the incoming purchase of UK9, a 9th C17 strategic cargo aircraft. A 10th serial number is also reserved for an eventual 10th aircraft.
The ambition to have 10 machines has been there for some time, and the lease or purchase of a further 2 C17s was reportedly on the table lately, also because the withdrawal from Afghanistan will require powerful air transport capability. The NAO believes that there will be Strategic Airlift capability in excess of requirement from 2016 onwards, but i do not quite agree: this is one of these capabilities that very rarely, if ever, can be in excess of requirements.


Future Strategic Tanker Aircraft - Voyager

The Voyager is currently operative as a transport and aeromedical evacuation platform only. It entered active service on April 4, 2012, and by December 2012 (when the third Voyager airplane arrived at Brize Norton) 16.000 personnel and other one million kgs had been airlifted in well over 1000 flying hours.

Of course, though, the main mission of Voyager is refuelling other airplanes in flight, and this is currently not yet validated due to leaks that were detected in various parts of the AAR flight envelope. Corrective measures have been agreed and are being implemented.

Air to Air refuelling IOC should be achieved within September this year, with one airplane fitted with both Wing pods and centerline fuselage station.
Air Tanker and the RAF, following problems in trials with the Cobham-designed High Speed-Variable Drag Drogue (HSVDD) fitted to the hoses of the Voyager have taken the decision to remove the HSVDD from the wing stations of Voyager tankers, reverting to the old Sergeant-Fletcher-designed drogue present on Tristar and VC10.

Aviation Week explains:

The HSVDD is designed to refuel aircraft at between 180 and 300 kt., a much wider speed range than previous drogue systems. However, a series of flight trials in 2011 found that the drogue or basket was venting and separately spinning, causing hose oscillation.

Although those oscillations were solved by mid-2012, results of trials with Tornado GR4 were still not satisfactory. The return to the Sergeant-Fletcher drogue has instead resulted in success with both Tornado and Typhoon.
The HSVDD will be maintained on the Centerline Fuselage Station, which is mostly intended for use in refueling of large aircrafts: trials have successfully been completed to validate AAR with C130J, and in 2014 the trials will be carried out with the E-3D Sentry AWACS.

FOC for FSTA is the provvision of a full fleet of 9 "core" tankers, 7 of which will be fitted for centerline refueling station and 5 fitted with it. The expected date for achievement of FOC is May 2014.
The centerline fuselage station is essential to provide Day and Night air refuelling to large aircrafts such as Sentry, C130 and, in future, A400 Atlas. The other 5 tankers, as known, are "on call" and might be released when not needed to serve as passenger airplanes on the civilian market. In reality, it has long dawned on the MOD that this is unlikely to happen, while it is more likely that european partners could buy Voyager AAR hours and services in the future. As mentioned earlier in this article, it had been planned that France would buy Voyager hours, but this plan did not go ahead.

To remedy to the potentially dramatic gap in AAR capability, the old Tristar tankers will serve beyond their planned OSD of July 2013, being in service until March 2014 at an extra cost of 7 millions.
The VC10 was expected to cease service in March 2013 but the RAF will try and operate them for at least a few months longer, out to September, but the closure of the maintenance line at St Athan will be the deciding factor: at one point, not far into the future, it'll be simply impossible to keep the VC10 flying any longer. 
 
The 3-point Voyager tankers (2 Wing stations plus centerline fuselage station) are known as Voyager KC3, the others as KC2. 
All aircrafts are fitted for a full DASS fit of electronic countermeasures and, following a 124 million measure in PR11 they are being fitted for platform protection (cockpit armor and other survivability features) for use in war theatres.



Astute-class submarines

The NAO report confirms that Astute has been trialing the installation and use of a "payload bay", which is actually the CHALFONT dry deck shelter for carriage of Special Boat Service operators and equipment, all the way up to the Swimmers Delivery Vehicles.

Planned expenditure for boats 1 to 3 reduced by 94 million pounds between April 2011 and March 2012.
Astute boat 4 and 5 had a significant cost growth connected to the slow-down of production connected to the delay of the Successor SSBN program to 2028. 

The NAO certifies that the delays imposed to the delivery of the 7 Astute submarines is preventing the Navy from achieving the planned availability of deployable SSNs.

The NAO reports that Astute boats 1 to 3 are forecast not to meet their Top Speed requirement, but all other requirements to be met. There is also an element of hope in the fact that the NAO notes that

initial trials in Boat 1 have been deliberately constrained but unrestricted trials will be conducted prior to Operational Handover.
so that HMS Astute could still demonstrate it can be as fast as the Navy hoped.

Boat 4 and 5 are expected to meet all requirements, but there are still risks, mainly due to some elements of planned capability not having been given the final go ahead and funding. In detail:

- Spearfish torpedo upgrade is now funded and on the way, with excellent progress to date
- An integrated communications and radar solution for Astute Boat 4 is now funded
- Naval Extremely/Super High Frequency Satcom Terminal approved by HM Treasury in December 2011 (not clear if the approval is for fitting at build only from boat 5 onwards, report is contraddictory as the same element is not funded in the Boat 4 table and funded in Boat 5 table)
- Astute Capability Sustainment Programme still awaiting HM Treasury approval

Despite the drama kicked up by the Guardian's articles, the Astute submarine program seems to be actually in good shape, and things appear to be improving.


Meteor BVRAAM

Technically, the missile is doing well, finally, in development and firing trials with a 3 months reduction in the trials period expected to be needed. However, the MOD was 11 months late in signing contracts and, worse, the Typhoon software development continues to be horrendously slow. The missile will be ready soon enough, but Typhoon won't get the software and the radar improvements necessary to properly employ Meteor in time. The FOC is described as full 6-missile fit, 2-way datalink and cockpit symbology and functionality, but the June 2017 ISD date could end up being valid for just the four missiles in semi-conformal positions under the fuselage.

The result is the slippage from an ISD of July 2015 to June 2017, with a consequent 50 million pounds cost to keep AMRAAM missiles stocks longer than planned. Worse, it might not be enough, and availability of AMRAAM missiles by 2017 risks being dangerously low.


JULIUS and Chinook New Buy 

The MK4 and 4A Chinooks upgraded are now entering in service and the first HC4 has even deployed to Afghanistan. However, the program accumulated several months of delay compared to earlier planned dates.

Delivery of the 14 new Chinooks (HC6) for service has also suffered delays and the MOD has prudently assumed that the IOC for the new Chinooks will take longer than hoped, now expecting it in November 2014, some 6 months later than earlier assumed.


Complex Weapons 

The NAO Report does not cover the Selective Precision Effect At Range (SPEAR) Capability 1 segment, unfortunately. This is relative to spiral development and evolution of the Paveway IV bomb, including the development and provvision of different kind of warheads, including a low-yeld, low collateral damage and a bunker-buster option. Improved capability against fast moving targets and longer glide ranges are also expected to be explored.

In July last year, Raytheon and Qinetiq completed ‘sled trials’ at the UK’s Pendine test range on the bunker-buster warhead, we know.

The Compact Penetrator warhead has the same outer mould-line and mass of the current Paveway™ IV enhanced Mk 82 warhead and has demonstrated a significantly increased penetration capability through the series of target engagement trials. Raytheon UK and QinetiQ have been working closely with Thales under the UK’s Weapon Technology Centre Compact Penetrator programme. The 25 month initiative will also undertake operational environment assessments, such as transportation, handling and air carriage.

Over the course of 2012, three orders for Paveway IV bombs were placed: a 60 million order in April to replenish stocks after operations in Libya, plus a 14 million in July and a further 25 million order in December.

The NAO does talk of SPEAR Capability 2, however: this is the development of the Brimstone missile.
Capability 2 Block 1, specifically, is the Brimstone 2 missile, a major improvement from the current UOR-derived Dual Mode Brimstone.
Brimstone 2 adds improved seeker and Insensitive Munition-compliant warhead and rocket motor, plus other improvements. It was to be introduced this year, but unfortunately trials imposed a 23 months delay as issues with both warhead and rocket motor emerged, the NAO reports. Warhead problems are fixed, lethality is confirmed and Critical Design Review passed, but the motor is still a problem. Seeker and electronics have been validated with 3 successful launches.
In 2013 there is going to be an IOC phase mating the improved seeker and electronics of Brimstone 2 to existing warheads and rocket motors, as an interim capability on the way to full release to service. A "minor concession" on performance has been agreed to enable MBDA to fix the rocket motor, presumably as a way to control costs, instead of wanting every tiny bit of capabilitity no matter what the cost. 

There was to be a SPEAR Capability 2 Block 2, but the decision was taken to delete this point of decision and just continue to spiral-develop the Brimstone 2. It is intended that in the early 2020s the Brimstone 2 or developments of it will replace the US-made Hellfire missile on the Apache attack helicopter. Hellfire OSD is 2021, and the NAO shows that Concept Phase has now begun on preparing Brimstone to act as replacement.
Brimstone 2 will be used on Tornado GR4 and Typhoon. F35 is not mentioned, at the moment. Integration on Typhoon is part of the Typhoon Future Capability Programme 2, for which we have no dates as of now. Almost certainly after 2015, unfortunately.
Tornado GR4 will be retired from service in March 2019, and by 2018 the RAF hopes to integrate Brimstone and Storm Shadow on the Typhoon.

A SPEAR Capability 2 Block 3 remains planned for the early 2020s (2022 or 2024). This could be a replacement missile in the same weight and mass class, or another development of the Brimstone.

SPEAR Capability 3 is a new 100-kg stand-off weapon (100 to 180 km range) specifically thought out for internal transport into the weapon bays of the F35, but we can expect to see it on Typhoon too, one day. The NAO provides a breakdown of the activity done so far, and the list is quite impressive, showing a great amount of progress:

Spear Capability 3
(i) Request for Quotations (RFQ) for seekers released - February 2011
(ii) Initial discussions about demonstration and manufacture/integration issues with Typhoon - May 2011
(iii) Assessment Phase subsystem downselect, Concept Design Review and Phase 2 Gate Review completed - July 2011
(iv) MBDA commenced launcher study because BRU-61 launcher found to be incompatible with chilled airframe design - August 2011
(v) Warhead supplier recommendation endorsed by Portfolio Management Board; Systems Design Review Complete; BAE Systems under contract for Phase 1 of Airframe and Propulsion Flight
Demonstration. Draft System Requirement Document issued - December 2011
(vi) Contract let with Hamilton Sunstrand for Turbojet Technical Assistance Agreement - January 2012

SPEAR 3 resembles the US Small Diameter Bomb and uses the same arrangement, with a launcher/pylon carrying four weapons. It is however a turbojet-powered missile and not a gliding bomb. Each F35B will carry a quadruple pylon in each weapon bay.

Another chapter is Fire Shadow, the loitering munition for the Royal Artillery, which saw the first 25 or more weapons delivered to the Army in March last year. Requirements have more or less been met, and development is continuing, but the MOD decided not to send Fire Shadow in Afghanistan for in-field experimentation and validation as had earlier been planned.
Fire Shadow is now "under review" within the Army, as is the whole of the unfortunate Indirect Fire Precision Attack program of which it is a part: the fear is that this "review" will ultimately be the final, lethal blow to IFPA, which has been so far a near complete failure:

- AS90 upgrade and 52 caliber barrel was cancelled
- Sensor fused 155 mm anti-tank shell was cancelled in 2010 after contract award in 2007
- LIMAWS(G) and (R) for lightweight self propelled gun and MLRS launcher were both cancelled
- Arming the Watchkeeper drone is an option on hold
- Fire Shadow seems to have an uncertain future at the moment
- Procurement of ATACMS (Large Long Range Rocket) for the british MLRS launchers was cancelled in Planning Round 11
- Procurement of a guided 155 mm shell is effectively on hold following deletion of funding in Planning Round 2011, but the intention is to deliver the precision artillery shell by 2018

The list is a graveyard, and makes it very evident that the effort of the Royal Artillery to modernize its kit has been frustrated again and again.

Much better news come from the Future Local Area Air Defence (FLAADS) which is the air defence missile system using CAMM as effector.
The NAO report suggests that not just the Maritime variant could be ready in November 2016, but the Land variant too (intended replacement for Rapier), although, as far as i'm aware, Rapier OSD is 2020.
Notable achievements include:

(i) Acheivement of Demonstration Phase Contract Award to deliver First of Class Platform - December 2011.
(ii) Successful completion of the System Preliminary Design Review - March 2012.
 
In 2016, FLAADS(M) will replace Sea Wolf on the first of the Type 23 frigates. It will also arm the Type 26 next generation frigates.

Finally, the Future Anti Surface Guided Weapon programme (FASGW) has hit a stumbling block. The Royal Navy and French Navy hope to join forces on FASGW(Heavy) to jointly develop the missile, but France is refusing to committ funding at this stage, and despite british pressure there has not yet been a decision on the way ahead.
The delay in launching the program is resulting in an expected delay of 19 months in entry in service of the new missile, which is needed to replace the old Sea Skua and arm the Wildcat HMA1 helicopter. This way, FASGW(H) will not be ready in 2015, and Sea Skua will have to be used for a longer period, with the very real risk that no money will be expended on integrating it on Wildcat, leaving the new helicopter clawless for the first part of its service life.

The definitive go-ahead has not been given to FASGW(L) either, but the Thales Light Multi-mission Missile is at a far higher technological readiness, and there is still time to order it in time for a 2015 entry in service on Wildcat.


The FALCON communications system finally entered service (Increment A for the Army and Increment C with the Royal Air Force signal unit), but it was several months late as well, and its UOR iteration for use in Afghanistan will not be ready in time either. The biggest plan change, however, is a March 2012 decision to distribute FALCON over the regiments of the Royal Signals (presumably the 5 Theatre Support Regiments) instead of concentrating it just in 30 and 22 Regiments.
This is presumably due to the conclusion that Brigade-level communications must be enhanced and FALCON is simply indispensable for all future deployments. This decision will have some impact on infrastructure expenditure in the next years, probably: under Project BORONA, 22 and 30 regiment (and a third regiment To Be Announced) are both due to be based in Beacon Barracks, Staffords, where infrastructure for storage and support of FALCON is to be built.
The NAO notes, in fact:

Whilst a lack of suitable garage space will not impact upon the capability, Army Headquarters is struggling to ensure that all intended locations have suitable secure storage for specialist items.

To enable the Urgent Operational Requirement, Falcon will utilise an Operational Training Equipment Pool and Operational Support Uplift Pool. This will be whole fleet management within 11 Signal Brigade. Not all receiving units will be able to garage Falcon but all units will have secure storage for access restricted items.

The NAO also notes that a series of improvements and interoperability mods to FALCON, developed for the UOR solution, are to be rolled out onto the whole fleet. Good news for once.
There is no mention of work on the next increment of FALCON, however, which is meant to introduce Network on the Move to maneuver forces. The Army's position is that improved communications are one of the most urgent improvements to be made, but at the same time financial realism means that the thick of the improvements will only go as low as to Battlegroup level, while the ambition was to bring network features all the way down to Company level.


The F35 and CVF sections are not of great interest this year as the NAO coverage does not reach the switch back to B and its implications.
It still lists, for example, a 31 million pounds saving from interuption of work on the Shipborne Rolling Vertical Landing technique for the F35B due to the switch to C variant, but it has been undisclosed in these days that, as part of the return to B, SRVL activities have restarted.
It has also been announced that this winter the Ski Jump for HMS Queen Elizabeth will be shipped to Rosyth, despite the fact that it has not even been ordered yet. It would be great to have informations on these changes, but they are outside the period covered by the 2012 report.

On CVF we learn that HMS Queen Elizabeth, in the plan that would have seen HMS Prince of Wales fitted with catapults and wires, would have served for just around 9 months for ship trials and validation activies before being mothballed.
It is hoped that the return to STOVL will mean both carriers are kept and put in service.


Regarding Wildcat helicopters, the NAO report confirms that the requirement, following PR11 options exercised, is for 66 helicopters:

30 Wildcat AH1 (Army Helicopter 1 - battlefield reconnaissance)
8 Wildcat LAH1 (Light Assault Helicopter 1 - 4 converted AH1 airframes and 4 additional, new airframes)
28 Wildcat HMA1 (Helicopter Maritime Attack 1 - naval variant)

The reason why we continually hear the ministers speak about 62 helicopters is that funding has currently been set aside in Core Budget for 34 AH1 and 28 HMA1 machines: negotiations and decision-making to include the LAH order in the Core Budget haven't yet concluded. The decision is expected this year.
The LAH is expected to be destined to replace the Lynx AH7 helicopters used by 657 Army Air Corps squadron, which flies in support of Special Forces.
The AAC expects to have four squadrons on the AH1 Wildcat. The squadrons will be all under 1st Regiment Army Air Corps, following the merge with 9 Regiment, as announced in Army 2020. The regiment will be based in Yeovilton, alongside the Navy's own Wildcats and the common training facility.
6 Regiment, the reserve element of the Army Air Corps, expects to stand up a new reserve squadron  to support the Wildcat force. 

There is not yet certainty about the exact composition of the naval order, either: for what i've heard, 4 of the 28 helicopters for the Royal Navy will actually be in AH1 configuration because destined to the Royal Marines of 847 NAS.
The remaining 24 machines, all HMA1, would be distributed 5 in 702 NAS for training and 19 in 815 NAS, to form 19 Small Ship Flights. The Merlin HM2 will, i believe, continue to provide 6 Small Ship Flights for frigates and two squadrons for "large deployments" (up to 6 helos at a time, on carriers or large RFA vessels), even after the reduction to just 30 airframes as part of the upgrade to HM2. 

The Wildcat AH1 risks being not fully capable because fitting of the Bowman Combat and Infrastructure Platform is not yet funded.
Similarly, the Wildcat HMA1 has not yet been given funding for the installation of the Data Link 22 (which in the next few years will replace Link 11, which works only in Line Of Sight), limiting the capability of the helicopter to share data Beyond Line of Sight.
The Royal Navy is prioritizing surface ships when it comes to funding of Data Link 22, but fitting it to Merlin and Wildcat will be a priority in the near future.

The Wildcat AH1 should be in service in August 2014: this represents a delay of 7 months, due to the training facility having been ordered only recently. The Full Mission Simulator won't be operative before december 2013, the Cockpit Procedures Trainer is only planned to go live in February 2014, the Aircraft Systems Trainer in November 2013 and Weapons & Avionics training solution in February 2014. This of course makes much harder to prepare personnel.
The HMA1 variant should still manage to enter service in January 2015.

 


Type 26 details from BAE


You really do not want to miss the latest article up at Navy Recognition on the Type 26 frigate. They have, after long waiting and big efforts, managed to obtain answers from BAE to several questions raised by the new Type 26 model shown at Euronaval last year.

If you do follow my blog from some time, though, you already know all the answers: my independent analysis of the model, published in October last year, was entirely correct:

- Mainmast design has been improved
- The 24 main VLS cells are Strike Lenght (not yet determined if it'll be MK41 or Sylver A70 though, but what matters is that they will be cruise-missile sized)
- The big white radomes on the mainmast are, as i had guessed, for the SCOT 5 satcom system.
- The white tubes near the missile silo are exactly the same decoy launchers i had said they were.

Pardon the shameless self-celebration, but i'm proud to see i was right and able to give such an accurate update on the state of the Type 26 design process.
I'll do my best to be always just as accurate and timely!